武漢市軌道交通8號(hào)線二期工程
XXXX土建工程
XXXX站主體結(jié)構(gòu)施工
專項(xiàng)方案
編制人:___________________
審核人:___________________
批準(zhǔn)人:__________________
XXXXX公司
武漢軌道交通8號(hào)線二期XXXX項(xiàng)目經(jīng)理部
2017年10月16H
目錄
第1章編制說明........................................................................1
1.1編制依據(jù)........................................................................1
1.2編制目的........................................................................1
第二章工程概況.........................................................................2
2.1總體概況.........................................................................2
2.2車站周邊環(huán)境....................................................................3
2.3主體結(jié)構(gòu)設(shè)計(jì)概況................................................................4
2.3.1結(jié)構(gòu)尺寸..................................................................4
2.3.2混凝土強(qiáng)度等級(jí)............................................................6
2.3.3混凝土保護(hù)層..............................................................7
2.4地形地貌.........................................................................7
2.5工程地質(zhì)情況...................................................................8
2.5.1工程地質(zhì).................................................................8
2.5.2水文地質(zhì)情況.............................................................9
第三章總體施工部署....................................................................11
3.1結(jié)構(gòu)分段.......................................................................11
3.2平面布置.......................................................................12
3.3豎向施工.......................................................................12
3.3.2豎向分層................................................................13
3.3.3施工工序................................................................13
3.4模板方案概述....................................................................15
3.4.1側(cè)墻模板..................................................................15
3.4.2中板、頂板模板...........................................................15
3.4.3柱模板....................................................................15
2.3.4梁模板..................................................................16
3.5資源配置計(jì)劃....................................................................16
3.5.1勞務(wù)人員配置............................................................16
3.5.2機(jī)械配置................................................................17
3.5.3主要儀器配置............................................................17
3.5.4主要材料投入計(jì)劃........................................................18
3.6工期計(jì)劃.......................................................................19
3.7交通組織......................................................................21
3.7.1混凝土交通組織..........................................................21
3.7.2場(chǎng)區(qū)內(nèi)交通..............................................................22
3.8組織機(jī)構(gòu)及職責(zé)................................................................22
3.9作業(yè)負(fù)責(zé)人及任務(wù)劃分..........................................................23
第四章鋼筋施工方案....................................................................23
4.1混凝土保護(hù)層厚度...............................................................23
4.2鋼筋的錨固與搭接..............................................................24
4.3鋼筋放樣......................................................................24
4.4板、墻開洞構(gòu)造措施............................................................25
4.5鋼筋后臺(tái)加工..................................................................25
4.5.1鋼筋調(diào)直.................................................................25
4.5.2鋼筋除銹.................................................................25
4.5.3鋼筋切斷.................................................................25
4.5.4切斷質(zhì)量要求.............................................................25
4.5.5鋼筋彎曲.................................................................25
4.6鋼筋綁扎與安裝施工準(zhǔn)備.........................................................26
4.7頂板、底板撐筋的安裝...........................................................26
4.8底板縱梁加固措施...............................................................27
4.9墊塊的布置......................................................................27
4.10底板頂板鋼筋在格構(gòu)柱處的連接方式.............................................28
4.11鋼筋的連接施工工藝............................................................28
4.11.1套筒直螺紋連接施工藝....................................................29
4.11.2化學(xué)植筋................................................................29
4.12預(yù)埋插筋施工工藝..............................................................30
4.13各部位鋼筋綁扎具體要求........................................................31
4.13.1梁.....................................................................31
4.13.2底板...................................................................32
4.12.3墻體...................................................................33
4.13.4樓板(頂板)...........................................................33
4.13.5柱.....................................................................34
4.14預(yù)埋件控制...................................................................34
4.14.1車站預(yù)埋件及預(yù)留孔洞質(zhì)量控制要點(diǎn)......................................34
4.14.2各專業(yè)預(yù)埋件及預(yù)留孔洞質(zhì)量技術(shù)要點(diǎn)....................................35
4.14.3車站土建預(yù)埋件及預(yù)留孔洞質(zhì)量管理措施..................................36
第五章雜散電流施工....................................................................37
5.1雜散電流施工工藝..............................................................37
5.2連接端子施工..................................................................39
5.3雜散電流防護(hù)對(duì)結(jié)構(gòu)鋼筋的焊接要求.............................................40
第六章模板及支撐體施工方案...........................................................40
第七章混凝土施工方案.................................................................40
7.1混凝土供應(yīng).....................................................................40
7.1.1混凝土罐車選擇...........................................................40
6.1.2天泵布置及澆筑形式.......................................................41
7.2商品碎的冬季施工措施...........................................................41
7.3混凝土運(yùn)輸.....................................................................43
7.4混凝土供貨驗(yàn)收.................................................................43
7.5混凝土澆筑.....................................................................43
7.5.1混凝土澆筑和振搗的要求..................................................43
7.5.2底板混凝土施工..........................................................44
7.5.3側(cè)墻(中柱)混凝土施工..................................................45
7.5.4中板、頂板混凝土施工....................................................46
7.5.5混凝土澆筑控制要點(diǎn).......................................................47
7.6混凝土養(yǎng)護(hù).....................................................................48
7.6.1一般季節(jié)混凝土養(yǎng)護(hù)......................................................48
7.6.2冬期施工的人工養(yǎng)護(hù)方法:................................................48
7.7預(yù)防泵管堵塞措施...............................................................49
7.8施工縫及變形縫施工............................................................49
第八章成品保護(hù)........................................................................50
8.1鋼筋保護(hù).......................................................................50
8.2模板保護(hù)......................................................................50
第九章監(jiān)測(cè)施工方案....................................................................50
9.1測(cè)點(diǎn)布置......................................................................50
9.2沉降觀測(cè)......................................................................51
9.3監(jiān)測(cè)措施......................................................................51
第十章安全生產(chǎn)保證措施................................................................52
10.1安全目標(biāo)......................................................................52
10.2安全施工原則..................................................................52
10.3安全保證組織機(jī)構(gòu)..............................................................52
10.4危險(xiǎn)源辨識(shí)....................................................................53
10.5安全保證措施.................................................................55
10.5.1預(yù)防坍塌事故安全技術(shù)措施..............................................55
10.5.2預(yù)防負(fù)高空墜落事故安全技術(shù)措施.......................................56
10.5.3混凝土澆筑技術(shù)安全措施................................................57
10.5.4機(jī)械施工安全注意事項(xiàng)..................................................57
10.5.5支架施工安全注意事項(xiàng)..................................................58
10.5.6基坑滑坡坍塌應(yīng)急措施..................................................59
10.5.7鋼支撐機(jī)械碰撞應(yīng)急措施................................................59
第十一章質(zhì)量保證措施..................................................................60
11.1質(zhì)量標(biāo)準(zhǔn)......................................................................60
11.2質(zhì)量保證措施.................................................................61
11.2.1鋼筋質(zhì)量管理措施......................................................61
11.2.2材料進(jìn)場(chǎng)檢驗(yàn)保證措施..................................................62
11.2.3模板支架質(zhì)量保證措施..................................................64
11.2.4混凝土施工質(zhì)量控制措施................................................64
11.3常見質(zhì)量問題的發(fā)生原因及防治措施.............................................67
11.3.1蜂窩產(chǎn)生的原因........................................................67
11.3.2蜂窩防治的措施。.....................................................67
11.3.3麻面產(chǎn)生的原因........................................................67
11.3.4麻面防治的措施........................................................68
11.3.5孔洞產(chǎn)生的原因........................................................68
11.3.6孔洞防治的措施........................................................68
11.3.7露筋產(chǎn)生的原因........................................................68
11.3.8露筋防治的措施........................................................69
11.3.9縫隙、夾層產(chǎn)生的原因..................................................69
11.3.10縫隙、夾層防治的措施.................................................69
11.3.11缺棱掉角產(chǎn)生的原因...................................................70
11.3.12缺棱掉角防治措施.....................................................70
11.3.13表面不平整產(chǎn)生的原因.................................................70
11.3.14表面不平整防治措施...................................................70
11.3.15強(qiáng)度不夠,均質(zhì)性差產(chǎn)生的原因........................................70
11.3.16強(qiáng)度不夠,均質(zhì)性差防治措施..........................................71
第十二章文明施工保證措施..............................................................71
第十三章應(yīng)急預(yù)案......................................................................72
13.1機(jī)構(gòu)設(shè)置.......................................................................72
13.2人員分工與職責(zé)................................................................72
13.3應(yīng)急救援工作程序..............................................................73
13.4應(yīng)急措施.......................................................................73
12.4.1模板支架倒塌應(yīng)急措施....................................................73
12.4.2高處墜落事故應(yīng)急準(zhǔn)備與響應(yīng)預(yù)案.........................................74
12.4.3電擊事故應(yīng)急準(zhǔn)備與響應(yīng)預(yù)案.............................................75
13.5恢復(fù)生產(chǎn)及應(yīng)急搶險(xiǎn)總結(jié)........................................................75
13.6預(yù)案管理與評(píng)審改進(jìn)............................................................76
武漢軌道交通8號(hào)線二期XX標(biāo)土建工程
XXXX站主體結(jié)構(gòu)施工專項(xiàng)方案
第1章編制說明
1.1編制依據(jù)
(1)武漢市軌道交通8號(hào)線二期工程XXXX土建工程XXXX站主體結(jié)構(gòu)施工
圖紙、業(yè)主提供各參考資料等。
(2)《武漢市軌道交通8號(hào)線二期工程第五標(biāo)段XXXX站巖土工程詳細(xì)勘
察報(bào)告》(湖北省地質(zhì)勘察基礎(chǔ)工程公司)。
(3)武漢市軌道交通8號(hào)線二期工程XXXX土建工程實(shí)施性施工組織設(shè)計(jì)。
(4)相關(guān)施工技術(shù)規(guī)范及國(guó)家有關(guān)安全、質(zhì)量、工程驗(yàn)收標(biāo)準(zhǔn)。
表17主要規(guī)范一覽表
序號(hào)標(biāo)準(zhǔn)名稱標(biāo)準(zhǔn)編號(hào)
1《大體積混凝土施工規(guī)范》GB50496-2009
2《地下鐵道工程施工及驗(yàn)收規(guī)范》(2003版)GB50299-1999
3《地下工程防水技術(shù)規(guī)范》GB50108-2008
4《地下防水工程質(zhì)量驗(yàn)收規(guī)范》GB50208-2011
5《建筑地基基礎(chǔ)設(shè)計(jì)規(guī)范》GB50007-2011
6《建筑地基處理技術(shù)規(guī)范》JGJ79-2012
7《混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50204-2015
8《鋼筋焊接及驗(yàn)收規(guī)程》JGJ18-2012
9《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范》(附條文說明)JGJ46-2005
10《建筑施工碗扣式鋼管腳手架安全技術(shù)規(guī)范》JGJ166-2008
11《鋼筋機(jī)械連接技術(shù)規(guī)程》(附條文說明)JGJ107-2010
13《建筑施工模板安全技術(shù)規(guī)范》JGJ-162-2008
14《建筑施工碗扣式鋼管腳手架安全技術(shù)規(guī)范》JGJ166-2016
15住房與城鄉(xiāng)建設(shè)部建質(zhì)[2009]87號(hào)文建設(shè)部文件
16住房與城鄉(xiāng)建設(shè)部建質(zhì)[2009]254號(hào)文建設(shè)部文件
1.2編制目的
武漢市軌道交通8號(hào)線二期工程XXXX土建工程XXXX站主體結(jié)構(gòu)工程為本標(biāo)
段關(guān)鍵性、重點(diǎn)性工程。為確保主體結(jié)構(gòu)能規(guī)范化、合理化施工,并做到科學(xué)管
理、精心組織,能按各節(jié)點(diǎn)工期要求,“優(yōu)質(zhì)、高效、安全、快速”完成主體結(jié)
構(gòu)施工,特編制此方案,以指導(dǎo)現(xiàn)場(chǎng)施工。
第二章工程概況
2.1總體概況
本工程為武漢軌道交通8號(hào)線二期XXXX,施工范圍為省農(nóng)科院站?
XXXX站區(qū)間(盾構(gòu))、XXXX站(明挖)、XXXX站?野芷湖站(不含)區(qū)
間(盾構(gòu))、野芷湖出入場(chǎng)段線(盾構(gòu)+明挖),共1車站2區(qū)間1出入線。XXXX
站設(shè)計(jì)為地下二層單柱島式站臺(tái)車站(其中地下一層為站廳層、地下二層為站臺(tái)
層),車站總長(zhǎng)554.06m,標(biāo)準(zhǔn)段外包總寬21.3m,站臺(tái)長(zhǎng)度為186米,站臺(tái)寬
度12m。
XXXX站圍護(hù)結(jié)構(gòu)端頭井01軸?03軸、65軸?67軸采用1000mm厚地連
墻十四道支撐圍護(hù),其中第一、二、三道為混凝土支撐,第四道為。800壁厚16mm
的鋼管支撐,并設(shè)一道鋼換撐;03軸?39軸、41軸?43軸采用1000mm厚地連
墻十五道支撐圍護(hù),其中第一道為混凝土支撐,其它各道均為。800壁厚16mm
的鋼管支撐,并設(shè)一道鋼換撐;43軸?48軸、50軸?65軸采用1000mm厚地
連墻+四道支撐圍護(hù),其中第一道為混凝土支撐,其它各道均為0800壁厚16mm
的鋼管支撐,并設(shè)一道鋼換撐;39軸?41軸采用1000mm厚地連墻+五道支撐
圍護(hù),五道均為混凝土支撐,并設(shè)一道鋼換撐;48軸?50軸采用1000mm厚地
連墻+五道支撐圍護(hù),五道均為混凝土支撐,并設(shè)一道鋼換撐。
車站共設(shè)置4個(gè)出入口、2組風(fēng)亭、1個(gè)安全出口(兼消防救援),出入口
分設(shè)于交叉路口的三個(gè)象限,風(fēng)亭分設(shè)車站南北兩端。車站具體平面位置示意下
圖所示意:
2
L
t
一
圖2-1車站平面位置示意圖
2.2車站周邊環(huán)境
車站位西側(cè)是XXXX新村及創(chuàng)意產(chǎn)業(yè)園創(chuàng)意天地,站位東側(cè)是保利心語住
宅區(qū)。周邊現(xiàn)狀為商業(yè)建筑、辦公建筑以及居住區(qū)等。
本站范圍內(nèi)原有10KV電力管群、信息網(wǎng)絡(luò)、DN300自來水,燃?xì)狻⒂辍?/p>
污水管開挖前均已遷改至兩側(cè)疏解便道下,施工區(qū)域內(nèi)無管線影響。
表2.2-1基坑周邊管線調(diào)查情況表
序號(hào)類型材質(zhì)斷面埋深施工影響處理方式
銅/光BH200*20000.42m車站主體施工遷改
銅/光中1000.35m車站主體施工遷改
1光纖銅/光BH400*2000.8m車站主體施工遷改
銅/光BH300*2001.2m車站主體施工遷改
2天然氣鋼①325中壓1.85m車站主體施工遷改
3電力銅8111000*8005根10KV0.87m車站主體施工遷改
4給水鑄鐵中3001.53m車站主體施工遷改
碎①20002.9m車站主體施工遷改
5雨水
性03003.02m車站主體施工遷改
6污水碎①4003.58m車站主體施工遷改
3
2.2.1管線改遷后情況統(tǒng)計(jì)
編號(hào)專業(yè)管徑材質(zhì)埋深走向距車站距離備注
1給水JS0500鑄鐵0.85~1.60東西走向4.76m~14.45m
排水WS0600HDPE4.23~5.30東西走向2.3m^l2.Im
2
排水YScD1000/2000PE3.04~4.30東西走向3.3m^l3.Im
BH1500*800銅0.8~2.5東西走向7.2m^l6.9m4+1根110KV
3電力DL
BH500X500銅0.3飛.5東西走向2.4m^ll.2m15孔10KV
銅/光(空
4電信DXBH400*2000.61.22東西走向6.9m~16.5m
管)
5燃?xì)釺R①325PE1.8~2東西走向5.9nT15.6m中壓
2.3主體結(jié)構(gòu)設(shè)計(jì)概況
2.3.1結(jié)構(gòu)尺寸
本車站總長(zhǎng)554.06m,標(biāo)準(zhǔn)段寬21.3m,主體結(jié)構(gòu)頂板覆土厚度約3.757?
4.464m,底板埋深約18.987-19.694m0車站主體采用地下兩層雙跨(局部三跨)
的鋼筋混凝土箱型框架結(jié)構(gòu),車站標(biāo)準(zhǔn)段框架柱距一般為縱向8.5m,縱向框架柱
尺寸為800X1000?1400。馬野區(qū)間左線端頭井負(fù)二層凈空11.235m、負(fù)一層凈
空5.05,馬野區(qū)間右線端頭井負(fù)二層凈空9.28m、負(fù)一層凈空5.05,省馬區(qū)間
及出入場(chǎng)線端頭井負(fù)二層凈空7.88m、負(fù)一層凈空5.05,標(biāo)準(zhǔn)段負(fù)二層凈空
6.39m、負(fù)一層凈空5.05m。標(biāo)準(zhǔn)段站臺(tái)板高度1.59m,端頭井回填素混凝土高度
1.49m,主體結(jié)構(gòu)設(shè)計(jì)指標(biāo)及結(jié)構(gòu)橫斷面和結(jié)構(gòu)尺寸如下。
4
§_
\DKZLI'H;MU⑷,
1203x200)I2OCX2OOT
’43X1200
1003x903
1
gmiu605。60WI1450zW,5
…TTtnt
「一二口
/YI器區(qū)
’——尸一1ml⑼,
ICOOxIOOOIWCTOW
I40DX12O)
KZ1
iom>zira
-01的佰.聞)2MLM修俾.
________ZS-
1690(5004)
-3180(3513)
乃-0_______________
?
圖2-2省馬區(qū)間盾構(gòu)井段橫斷面圖
;21燦群號(hào)
CK2L4
m250tl6.2圖
圖2-3馬野區(qū)間右線盾構(gòu)井段橫斷面圖
5
:/:.?.:.st"a
7
11,060(1&依)I
I§
5.1以10切1)尹州友971)
出
入
冷
燒
珞
中
心
線
1I砌
圖2-4馬野區(qū)間左線盾構(gòu)井段橫斷面圖
圖2-5單柱橫斷面圖
2.3.2混凝土強(qiáng)度等級(jí)
6
(1)主體結(jié)構(gòu)頂、底板及其梁、側(cè)墻及壁柱、側(cè)墻、梁及柱:C35防水混
凝土;抗?jié)B等級(jí):P8o
(2)主體結(jié)構(gòu)中樓板及其梁:C35
(3)土建風(fēng)道、樓梯板及其梁、柱、扶梯柱:C35
(4)主體結(jié)構(gòu)框架柱:C50;暗柱:C35
(5)回填素混凝:C30;底板下素混凝土墊層:C20o
2.3.3混凝土保護(hù)層
(1)底板及其梁、頂板及其梁、側(cè)墻及其壁柱:迎水面45nlm、背水面35mm,
(2)框架柱:40mm
(3)中樓板及其梁:30mm
表2.3-1主體結(jié)構(gòu)設(shè)計(jì)標(biāo)準(zhǔn)
設(shè)計(jì)使用年限100年設(shè)計(jì)基準(zhǔn)期50年
結(jié)構(gòu)安全等級(jí)1級(jí)耐火設(shè)計(jì)標(biāo)準(zhǔn)一級(jí)
結(jié)構(gòu)抗震烈度7度抗震等級(jí)二級(jí)
結(jié)構(gòu)人防等級(jí)6級(jí)防水設(shè)計(jì)標(biāo)準(zhǔn)一級(jí)
允許裂縫寬度迎水面不大5二0.2mm,其它不大于0.3mm。
表2.3-2主體結(jié)構(gòu)主要構(gòu)件尺寸表
車站結(jié)構(gòu)部位尺寸/mm標(biāo)準(zhǔn)段剖面圖
頂板厚900
中板厚400
XXXX
底板厚1000
站
側(cè)墻厚800/900
800X1000-
中柱
1400
2.4地形地貌
XXXX站場(chǎng)地地形平坦,地勢(shì)起伏不大,坡降較緩,地面高程一般在20.83?
22.00米之間,擬建場(chǎng)地地貌單元屬長(zhǎng)江III級(jí)階地剝蝕堆積平原區(qū)(三級(jí)階地湖
7
積區(qū))。
2.5工程地質(zhì)情況
2.5.1工程地質(zhì)
場(chǎng)地分布地層自上而下可分為以下幾個(gè)單元層,各巖土層按不同巖性及工程
性能分為若干亞層,其分布情況及工程地質(zhì)特征描述如下:
(-)填土及第四系全新統(tǒng)一般黏性土
1、1T雜填土(Qml/):雜色,高壓縮性,由磚塊、碎石、塊石、片石、爐
渣等建筑及少量生活垃圾、黏性土混合而成(局部地表有15?30cm厚的碎、瀝
青地坪)。該層土結(jié)構(gòu)不均、土質(zhì)松散,堆積時(shí)間小于10年,場(chǎng)地均有分布,
層厚0.30?9.00m,土質(zhì)不均勻。
2、1-2素填土(Qml/):黃褐?灰褐,高壓縮性,由黏性土和少量碎石及生
活垃圾
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 畜牧良種繁殖資源保護(hù)與持續(xù)利用考核試卷
- 種子批發(fā)市場(chǎng)供應(yīng)鏈透明度與追溯技術(shù)考核試卷
- 紙質(zhì)航空航天材料研究進(jìn)展與應(yīng)用考核試卷
- 珠寶首飾行業(yè)科技創(chuàng)新與產(chǎn)業(yè)發(fā)展考核試卷
- 紡織品批發(fā)市場(chǎng)動(dòng)態(tài)監(jiān)測(cè)考核試卷
- 電磁輻射安全檢測(cè)考核試卷
- 毛皮制品加工企業(yè)生產(chǎn)過程質(zhì)量控制考核試卷
- 篷布產(chǎn)業(yè)標(biāo)準(zhǔn)化建設(shè)考核試卷
- 上饒衛(wèi)生健康職業(yè)學(xué)院《古文字學(xué)與古代漢語》2023-2024學(xué)年第二學(xué)期期末試卷
- 四川省成都西蜀實(shí)驗(yàn)2025屆初三數(shù)學(xué)試題5月8日第6周測(cè)試題含解析
- 社團(tuán)語言學(xué)習(xí)法課件
- 卷料加工中的跑偏與糾偏控制
- 波紋鋼裝配式檢查井通用技術(shù)規(guī)范
- 財(cái)務(wù)支出預(yù)算表模板
- 人力資源的5分鐘勞動(dòng)法
- 當(dāng)代學(xué)前兒童家庭教育的問題與對(duì)策研究 論文
- 小學(xué)語文五年下冊(cè)《習(xí)作:形形色色的人》說課稿(附教學(xué)反思、板書)課件
- 公務(wù)員錄用體檢操作手冊(cè)
- 建筑施工企業(yè)預(yù)結(jié)算制度
- 2023年中央民族大學(xué)事業(yè)編制人員招聘(共500題含答案解析)筆試歷年難、易錯(cuò)考點(diǎn)試題含答案附詳解
- 醫(yī)務(wù)人員手衛(wèi)生PPT
評(píng)論
0/150
提交評(píng)論