DL/T5190.3-××××
ICS
K
備案號:
中華人民共和國電力行業標準
DL/T5190.3-XXXX
P代替DL5190.3-2012
電力建設施工技術規范
第3部分:汽輪發電機組
Technicalspecificationforthermalpower
erectionandconstruction
Part3:steamturbinegeneratorunit
(征求意見稿)
XXX-XX-XX發布XXXX-XX-XX實施
國家能源局發布
DL5190.3—XXXX
II
DL5190.3—XXXX
目次
1總則................................................................................................1
2術語................................................................................................2
3基本規定........................................................................................5
3.1設備開箱檢驗及保管..............................................................................5
3.2土建工程..................................................................................................6
3.3設備及系統安裝......................................................................................7
3.4試運行......................................................................................................9
4汽輪機本體..................................................................................12
4.1一般規定................................................................................................12
4.2本體基礎................................................................................................12
4.3臺板與墊鐵............................................................................................14
4.4汽缸、軸承座及滑銷系統....................................................................18
4.5軸承和油擋............................................................................................23
4.6整體供貨的汽缸....................................................................................31
4.7汽輪機轉子............................................................................................33
4.8通流部分設備安裝................................................................................38
4.9減速器和盤車裝置................................................................................44
4.10汽輪機扣大蓋......................................................................................47
4.11基礎二次灌漿及養護..........................................................................52
4.12質量驗收應提交的項目文件..............................................................53
5汽輪機輔助設備..........................................................................57
5.1一般規定................................................................................................57
5.2凝汽器....................................................................................................58
5.3直接空冷凝汽器....................................................................................65
5.4間接空冷裝置........................................................................................71
III
DL5190.3—XXXX
5.5熱交換器................................................................................................74
5.6箱罐和除氧器........................................................................................76
5.7減溫減壓裝置........................................................................................78
5.8抽氣設備................................................................................................79
5.9汽水管道的吹掃和沖洗........................................................................81
5.10汽輪機真空系統嚴密性檢查..............................................................82
5.11汽輪機輔助設備試運行......................................................................83
5.12質量驗收應提交的項目文件..............................................................85
6汽輪機附屬機械..........................................................................88
6.1一般規定................................................................................................88
6.2一般離心泵............................................................................................95
6.3給水泵及其配套裝置..........................................................................100
6.4立式泵..................................................................................................104
6.5深井泵..................................................................................................116
6.6空冷風機和水塔風機..........................................................................119
6.7旋轉濾網..............................................................................................121
6.8真空泵安裝..........................................................................................122
6.9附屬機械分部試運行..........................................................................123
6.10質量驗收應提交的項目文件............................................................129
7燃氣輪機本體............................................................................132
7.1本體基礎..............................................................................................132
7.2墊鐵和可調固定器..............................................................................132
7.3臺板和支撐裝置..................................................................................132
7.4燃氣輪機本體......................................................................................132
7.5燃氣輪機進氣、排氣系統安裝..........................................................136
7.6基礎二次灌漿及養護..........................................................................138
7.7罩殼安裝..............................................................................................138
7.8質量驗收應提交的項目文件..............................................................138
8燃氣輪機附屬系統....................................................................141
IV
DL5190.3—XXXX
8.1設備及框架模塊安裝..........................................................................141
8.2附屬系統管道安裝..............................................................................143
8.3燃氣輪機附屬系統試運行..................................................................145
8.4質量驗收應提交的項目文件..............................................................147
9發電機和勵磁裝置....................................................................149
9.1一般規定..............................................................................................149
9.2軸承座及軸承......................................................................................153
9.3定子......................................................................................................154
9.4發電機轉子..........................................................................................158
9.5調整定子位置和封閉端蓋..................................................................161
9.6氫冷和水氫氫冷發電機的軸密封裝置及氣體冷卻系統..................163
9.7雙水內冷發電機進出水支座和冷卻器..............................................167
9.8冷卻水系統..........................................................................................171
9.9勵磁裝置..............................................................................................173
9.10質量驗收應提交的項目文件............................................................174
10調節保安裝置和油系統..........................................................177
10.1一般規定................................................................................177
10.2電液調節保安裝置............................................................................180
10.3汽門及其傳動機構............................................................................183
10.4離心式主油泵..........................................................................188
10.5調節油系統................................................................................190
10.6潤滑油系統................................................................................192
10.7氫冷發電機的密封油系統................................................................197
10.8油循環和油系統試運........................................................................199
10.9質量驗收應提交的項目文件............................................................203
11汽輪機本體范圍的管道..........................................................205
11.1一般規定............................................................................................205
11.2閥門安裝............................................................................................205
11.3管道安裝............................................................................................206
V
DL5190.3—XXXX
11.4質量驗收應提交的項目文件............................................................209
12起重設施..................................................................................210
12.1橋式起重機........................................................................................210
12.2電動(手動)葫蘆............................................................................218
12.3質量驗收應提交的項目文件............................................................219
13汽輪機化妝板、平臺、梯子和蓋板.....................................221
13.1汽輪機化妝板....................................................................................221
13.2平臺、梯子和蓋板............................................................................221
附錄A汽輪機臺板砂漿墊塊施工規定......................................223
附錄B汽缸密封涂料..................................................................225
附錄C常用密封材料品種及適用范圍......................................226
附錄D常用油脂品種及適用范圍..............................................228
附錄E汽輪機螺栓常用材料物理性能......................................231
附錄F用鋼絲找中心垂弧計算公式..........................................232
附錄G機組振動標準..................................................................233
附錄H油質等級標準..................................................................234
標準用詞說明..................................................................................237
引用標準名錄..................................................................................238
條文說明..........................................................................................240
VI
DL5190.3—XXXX
Contents
1Generalprovisions························································1
2Terms·······································································2
3Basicrequirement·························································5
3.1Equipmentumpackingandstorage······································5
3.2Civilworks······························································7
3.3Equipmentandsystemerection·········································7
3.4Trialrunofturbogenerators·············································9
4Steamturbine····························································12
4.1Generalrequirement···················································12
4.2Requirementsforfoundation···········································12
4.3Soleplateandshims····················································14
4.4Casing,bearingpedestalsandslidingkeysystem······················18
4.5Bearingandoilbaffle··················································23
4.6Integralcylinder·······················································31
4.7Steamturbinerotor····················································33
4.8Installationofequipmentinflowpassage······························38
4.9Turninggearandspeedreducer········································44
4.10Coveringofsteamturbine············································47
4.11Secondarygroutingandcuring·······································52
4.12Projectdocumentstobeprovidedbeforequalityacceptance·········53
5Auxiliaryequipments···················································57
5.1Generalrequirement···················································57
5.2Condenser······························································58
5.3Aircooleddevice······················································65
5.4Indirectairdevice······················································71
VII
DL5190.3—XXXX
5.5Heatexchanger························································74
5.6Tanksanddeaerator····················································76
5.7Attemperatorandpressurereducingdevice····························78
5.8Extractionequipments·················································79
5.9Purgingandflushingofsteam-waterpipelines·························80
5.10Leakagecheckofsteamturbinevacuumsystem·····················82
5.11Trialrunofsteamturbineauxiliaryequipment·······················83
5.12Projectdocumentstobeprovidedbeforequalityacceptance········85
6Accessorymachinery···················································88
6.1Generalrequirement··················································88
6.2Commoncentrifugalpumps············································95
6.3Feedwaterpumpunitsandtheirassociateddevices··················100
6.4Verticalpumps························································104
6.5Deepwellpumps·····················································116
6.6Aircoolingandwatercoolingfans···································119
6.7Rotatingfiter·························································121
6.8Vacuumpump························································122
6.9Trialrunofaccessorymachinery·····································123
6.10Projectdocumentstobeprovidedbeforequalityacceptance········219
7Gasturbine······························································132
7.1Requirementsforfoundation········································132
7.2Shimandfixator·····················································132
7.3Soleplateandsupportdevice·········································132
7.4Gasturbine···························································132
7.5Airintakeandexhaustsystems············································136
7.6Secondarygroutingandcuring······································138
7.7Enclosureofgasturbine····················································138
7.8Projectdocumentstobeprovidedbeforequalityacceptance··········138
8Gasturbineaccessorysystems·············································141
VIII
DL5190.3—XXXX
8.1Equipmentsandmoduleerection··········································141
8.2Pipingerectionofaccessorysystems·····································143
8.3Trialrunofaccessorymachinery··········································145
8.4Projectdocumentstobeprovidedbeforequalityacceptance··········147
9Generatorandexcitationdevice·····································149
9.1Generalrequirement··················································149
9.2Bearingseatandbearing·············································153
9.3Stator·································································154
9.4Generatorrotor·······················································158
9.5Statorpositionadjustmentandcoverclosing·························161
9.6Shaftsealingandgascoolingsystemofhydrogen-
cooledandwater-hydrogen-hydrogen-cooledgenerator············163
9.7Waterinlet/outletpedestalsandcooler·······························167
9.8Coolingwatersystem·················································171
9.9Excitationdevice·····················································173
9.10Projectdocumentstobeprovidedbeforequalityacceptance········174
10Control-protectingdeviceandoilsystem·························177
10.1Generalrequirement················································177
10.2Electro-hydrauliccontrolandprotectingdevice·····················180
10.3Steamvalveanditsdrivingadevice································183
10.4Centrifugalmainoilpump··········································188
10.5Controloilsystem···················································190
10.6Lubricatingoilsystem··············································192
10.7Sealingoilsystemofhydrogen-cooledgenerator···················197
10.8Trialrunofoilsystemandoilflushing······························199
10.9Projectdocumentstobeprovidedbeforequalityacceptance······203
11Pipingofsteamturbine············································205
11.1Generalrequirement···············································205
11.2Valvesandspecialparts·············································205
IX
DL5190.3—XXXX
11.3Installationofpiping················································206
11.4Projectdocumentstobeprovidedbeforequalityacceptance········209
12hoistingequipmentofthemainpowerhouse····················210
12.1Bridgecrane·························································210
12.2Electric(manual)hoist··············································218
12.3Projectdocumentstobeprovidedbeforequalityacceptance········219
13Enclosure,platformladderandcoverofsteamturbine·········221
13.1Enclosureofsteamturbine··········································221
13.2platformladderandcoverofsteamturbine·························221
AppendixARequirementsforconstructionofmortarand
padsforS/Tsoleplate····································223
AppendixBcylindercoating···········································225
AppendixCCommonsealingmaterialtypesandscope
ofapplication··············································226
AppendixDCommongreasetypesandscope
ofapplication··············································228
AppendixEPhysicalperformanceofcommonS/T
boltingmaterials··········································231
AppendixFSagcalculationformulaforcentering
withsteelwire············································232
AppendixGUnitvibrationcriterion··································233
AppendixHOilqualityratingcriterion······························234
Explanationofwordinginthiscode·····································237
Normativestandard························································238
Addition:Explanationofprovisions·····································240
X
DL5190.3—XXXX
1總則
1.0.1為了加強汽輪發電機組工程施工技術管理,進一步提高工
程施工質量,修訂DL5190.3—2012《電力建設施工技術規范》第
三部分。
1.0.2本部分適用于火力發電廠汽輪發電機組、燃氣-蒸汽聯合
循環發電機組、單循環燃氣發電機組、輔助設備及附屬機械的施
工。
1.0.3汽輪發電機組的施工應依據經批準的設計和設備制造廠技
術文件,如需修改或變更,應由設計單位、設備制造廠出具相應
的證明文件,辦理相關的審批手續。發電廠土建工程除滿足本規
范《電力建設施工技術規范第1部分:土建工程》的規定外,
特殊要求按本部分相關規定執行。
1.0.4汽輪發電機組的施工應按設備訂貨合同、技術協議及制造
廠有效技術文件的要求執行,如合同協議及制造廠技術文件無明
確要求或要求不全面時,按本部分規定執行。
1.0.5汽輪發電機組的施工,除應符合本部分規定外,還應執行
國家、行業現行有關標準規定。
1
DL5190.3—XXXX
2術語
2.0.1橢圓度ellipticity
圓柱形軸或者孔在某一橫剖面的不圓度,其數值為該橫剖面
最大直徑與最小直徑之差。
2.0.2不柱度non-cylindricity
圓柱形軸或孔通過軸中心線的軸向剖面上下線與平行線的偏
差。其數值為該軸或孔在軸向剖面上最大與最小直徑之差。要求
為正圓柱體的部件,不柱度表示偏離正圓柱要求的程度。
2.0.3錐度taper
圓錐、圓臺形狀回轉面與基準面的傾斜程度。對于圓錐形狀
其數值為圓錐基準面直徑與圓錐高度的比值,對于圓臺形狀其數
值為上下直徑之差與圓臺高度的比值。
2.0.4傾斜度tilt/(坡度)tilt(gradient)
直線或平面與基準線或基準面相交的傾斜程度。其數值為給
定的基準面或線長度內該面或線與基準面或線的最小距離與給定
長度的比值。
2.0.5平面度flatness
實際表面偏離標準平面的程度。其數值用實際平面距離標準
平面最遠點的距離值表示。
2.0.6不平行度non-parallelism
兩個相互平行的線或面間的不平行的程度。其數值為該二要
素間最大與最小垂直距離之差。
2.0.7不垂直度non-perpendicularity
兩條軸線、軸線與平面或兩平面之間所形成的角度與標準直
角之差。以單位長度內標準垂直線或面與所測線或面的最小距離
△表示,單位△/m。
2.0.8徑向晃度radialrunout
2
DL5190.3—XXXX
徑向晃度表示測量斷面所在的軸表面到軸中心線距離的偏離
程度。用百分表垂直指向被測斷面的軸中心線,轉子軸頸在支持
面上盤動,被測表面上各點讀數的最大與最小值之差,為軸頸在
該截面的徑向晃度。
2.0.9端面瓢偏endingrunout
端面瓢偏表示該端面與軸中心線不垂直的程度。在被測端面
接近直徑的周邊部位,相對180°位置各安放一個垂直于端面的百
分表,盤動轉子,兩表同時指示的最大差值減去最小差值的1/2
即為端面瓢偏值。
2.0.10大型水泵largepumps
出口公稱直徑大于400mm的高壓離心泵,以及入口公稱直
徑大于700mm的低壓泵。
2.0.11高速水泵high-speedpumps
額定轉速高于1500r/min的水泵。
2.0.12可調式汽封adjustablesteamseal
可調式汽封是一種隨著啟動過程中蒸汽壓力的逐漸增大而分
段閉合的汽封。其主要特點:啟動時,汽封塊張開,使動靜部分
達到最大間隙,避免了啟動過程中由于振動及變形而導致的碰磨。
隨著機組升速加負荷,汽封塊端部閉合,使動靜間隙減小,以減
少汽封的漏汽量從而提高機組的效率。
2.0.13空冷凝汽器air-cooledcondenser(ACC)
空冷凝汽器簡稱為ACC,指以空氣作為冷卻介質,使汽輪機
排汽凝結成水的表面式換熱器。
2.0.14相對振動relativevibration
相對振動是指轉軸和相應結構(例如軸承座或機殼)之間的
徑向位移量的測量值,如無特別說明,本部分中的“軸振動”均
指相對振動。
2.0.15絕對振動absolutevibration
絕對振動是指轉軸相對于某一慣性參考系的位移量的測量值。
3
DL5190.3—XXXX
2.0.16輔機故障減負荷試驗runbacktest
當發生部分主要輔機故障停運,機組最大出力低于給定負荷
時,測試控制系統將機組負荷快速降低到實際所能達到的出力,
并控制機組在允許參數范圍內繼續運行能力的過程,稱為輔機故
障減負荷試驗。
4
DL5190.3—XXXX
3基本規定
3.1設備開箱檢驗及保管
3.1.1設備到達現場后,應由建設、制造、監理、總包、施工、
設備保管等相關單位共同開箱查驗并記錄簽證。有缺陷的設備應
按合同約定進行處理。
3.1.2設備開箱檢驗時,裝箱單、說明書、質量證明文件、圖紙
等技術文件應齊全。
3.1.3設備裝卸和搬運應符合下列規定:
1應按箱上標識部位綁扎吊索及加襯墊物,并防止重心偏
移;
2對剛度較差的設備,應采取措施防止變形;
3應核實設備搬運途中經過的路面、橋梁等承載能力;
4碳鋼吊索不得與奧氏體不銹鋼材質的設備接觸。
3.1.4設備開箱檢查應符合下列規定:
1在開箱檢查時,應防止損傷和損壞設備及零部件。對裝有
精密設備的箱件,應注意對精密設備妥善保護;
2設備防腐涂料未清理前,不得轉動和滑動,清理檢查后應
用原防腐涂料進行防腐處理;
3需要添加潤滑劑等特殊要求的轉動設備,開箱檢查時不得
盤動;
4設備開箱檢查后暫不安裝時應重新封閉;露天放置的箱
件,應采取有效的防護措施;
5裝箱設備的配件及專用工具應成套保管。
3.1.5設備保管人員應熟悉設備保管規程,汽輪發電機組設備的
特殊保管要求,并做好保管記錄。
3.1.6設備安裝前保管應符合DL/T855《電力基本建設火電設備
5
DL5190.3—XXXX
維護保管規程》的規定。
3.1.7設備和器材應分區、分類存放,標識清晰,并應符合下列
規定:
1存放區域應有明顯的區界和消防通道,并具備可靠的消防
設施和有效的照明;
2大件設備的存放位置應根據施工順序和運輸條件,按照施
工組織設計的規定合理布置,以減少二次搬運;
3設備應支墊穩固、可靠,存放場地排水應暢通,并應采取
防撞、防凍、防潮、防塵和防傾倒等措施;
4存放地點和貨架應具備足夠的承載能力;
5海濱鹽霧地區和含有腐蝕性的環境,應采取特殊措施,防
止設備銹蝕;
6儀器、儀表及精密部件應存放在貨架上或按要求放置在保
溫庫內;
7管材、管件和部件應標識明確、分類存放,避免混淆;
8充氮保護的設備,應定期檢查記錄氮氣壓力及設備密封情
況。當壓力低于3.5kPa時,應及時補充氮氣;
9燃氣輪機濾芯保管應有防潮措施。
3.1.8隨設備提供的材料應有質量證明文件,在核查中對材料質
量有質疑時,應進行復檢。
3.1.9外委加工和現場加工配制的成品或半成品,應按本部分的
有關規定進行檢驗,合格后方可使用。
3.1.10安裝就位的設備應加強成品保護,防止設備在安裝期間損
傷、銹蝕、凍裂;經過試運行的主要設備,應根據制造廠對設備
的有關要求,制定維護保養措施,經監理審定后,妥善保管。
3.2土建工程
3.2.1汽輪發電機組安裝前期,由監理組織土建專業、安裝專業
6
DL5190.3—XXXX
進行圖紙會檢。
3.2.2土建施工期間,安裝專業應做如下工作:
1施工準備時,對預留孔洞、預埋件、汽輪發電機組基座及
主要附屬設備基礎等標高、中心線、地腳螺栓孔位置等重要幾何尺
寸應進行校核;
2澆灌前,安裝單位應參加基座澆灌前的中間核查工作;
3起吊重型設備需要的起吊設施的基礎、錨固點及為超負荷
起吊而對建筑結構進行的加固方案,應在土建施工前與設計單位、
監理單位和土建施工單位確定;
4因吊裝大型設備而預留的鋼結構、基礎或墻體,應在土建
施工前由設計單位、監理單位和土建施工單位等有關單位確認。
3.2.3交付安裝的土建工程應具備下列條件:
1行車軌道安裝完畢,二次灌漿的混凝土已達到設計強度,
并經驗收合格;
2主輔設備基礎、基座混凝土已達到設計強度的70%以上,
模板已拆除;
3廠房封閉,屋面止水;
4廠房內的各基礎縱橫中心線、標高標識和基礎沉降觀測點
清晰、齊全;
5各層平臺、通道、梯子、欄桿、踢腳板裝設完畢且焊接牢
固,主機周邊孔洞有可靠的臨時蓋板或圍欄;
6廠房內的管溝、泵坑、排水溝及集水井等清潔,排水暢通;
7消防設施可靠;
8建筑物和基礎上的基準線與基準點標識清晰、齊全。
3.3設備及系統安裝
3.3.1設備安裝應根據下列技術文件進行:
1制造廠設備質量證明書、說明書、圖紙等;
7
DL5190.3—XXXX
2專業施工組織設計及作業指導書;
3綠色施工專項措施。
3.3.2施工前,工程技術人員應對施工人員進行技術交底。
3.3.3汽輪發電機組的施工場地應符合下列規定:
1臨時放置設備和材料的場地應滿足相應載荷要求;
2施工地點環境溫度宜保持在5℃以上;
3水、電等力能供應應滿足施工需求,照明充足;
4基建施工和生產運行區域的隔離設施應有明顯標識;
5起重設備應具備使用條件。
3.3.4設備安裝時,建筑物的保護應符合下列規定:
1不得任意變更或損壞建筑物結構;
2禁止在建筑物金屬結構上任意施焊、切割;
3不得隨意在建筑混凝土結構上錘擊、開孔,不得鑿開混凝
土保護層在鋼筋上焊接、切割。
3.3.5設備安裝前,如發現有損壞或質量缺陷,應及時通知有關
單位共同檢查確認,并進行處理。
3.3.6設備中的零部件和緊固件安裝前應按DL/T438《火力發電
廠金屬技術監督規程》和DL/T439《火力發電廠高溫緊固件技術
導則》規定進行光譜、無損探傷、金相、硬度等檢驗,并與制造
廠技術文件要求相符。
3.3.7設備及部件的清理應符合下列規定:
1設備部件內部的雜物、油垢、銹跡應清理干凈并及時封閉;
2設備的精密加工面不應用鏟刀、銼刀除銹,不得用火焰除
油;
3用蒸汽吹掃的部件應及時去除水分;
4清理軸頸和軸瓦時不得損傷其表面;
5清理后的設備及零部件應分類存放,并防止二次污染。
3.3.8汽輪發電機組施工應符合下列規定:
1設備的解體檢查、測量和調整應符合制造廠的技術文件要
8
DL5190.3—XXXX
求;
2拆卸設備部套時應做好標記、使用專用工器具,并不得強
行拆裝;
3拆下的零部件應妥善保管。
3.3.9隱蔽工程的安裝檢查應符合下列規定:
1進入隱蔽區域、設備內部清理和檢查的人員,應穿無紐扣
的專用工作服,鞋底無鐵釘并擦拭干凈;
2設備及管道封閉前,應指定專人檢查,確認內部無雜物后
辦理簽證;
3設備及管道的封閉應明顯,牢固、可靠;
4不得在已最終封閉的設備或管道上施焊、開孔、拆封。
3.4試運行
3.4.1汽輪發電機及其附屬機械、輔助設備試運時現場應具備下
列條件:
1廠區場地平整,道路暢通;
2試運范圍內的施工臨時設施應拆除并清理干凈,現場溝
道、孔洞蓋板齊全,臨時孔洞應裝設護欄或蓋板,平臺的樓梯、
通道、欄桿及護板應安裝完畢;
3消防器材滿足試運要求,消防系統具備投用條件,事故排
油系統具備使用條件;
4試運機組范圍內的各層地面施工完畢;
5生活用的上下水道暢通,衛生設施能正常使用;
6廠房和廠區的排水系統、工業廢水處理系統應正常投用;
7照明系統應正常投用,事故照明系統完整、可靠并處于備
用狀態;
8試運時室內溫度宜保持5℃以上;
9電話等通信設備安裝完畢,應正常投用;
9
DL5190.3—XXXX
10與試運有關的空調系統應正常投用。
3.4.2汽輪發電機組及附屬機械、輔助設備和系統,在試運前應
具備下列條件:
1設備及系統按規定安裝完畢,并驗收合格,安裝技術記錄
齊全;
2設備及管道的保溫工作已完成,管道支吊架已調整結束;
3基礎混凝土及二次灌漿層達到設計強度;
4操作電源、動力電源、壓縮空氣氣源可靠;
5水位計和油位計標識清晰、顯示正確;
6轉動機械已按要求加潤滑油、脂,油位正常;
7工業水系統具備投用條件且沖洗潔凈;
8閥門應逐個檢查調整完畢,全行程啟閉(停)靈活、開
度準確且無卡澀;
9試運范圍內的容器,已按要求清理和沖洗;
10各指示和記錄儀表及信號、聲光報警裝置已裝設齊全,
并經校驗調整準確;
11試運設備或系統已掛牌并標識清晰,表計指示正確且在
有效期內;
12啟動用汽源應充足并穩定,其壓力和溫度應能符合軸封
供汽、汽動給水泵、除氧器等用汽的要求;
13自動控制部分及精密部套的通風、空調裝置應投用;
14試運設備的保護裝置已校驗合格并投用。
3.4.3汽輪發電機組的分部試運調試措施已批準。
3.4.4汽輪發電機組整套啟動前應完成下列工作:
1汽水管道的吹掃和沖洗;
2冷卻水系統通水試驗和沖洗;
3化學水系統沖洗、充填藥劑、調整試運行,并能供給足量
合格的除鹽水;
4真空系統嚴密性檢查;
10
DL5190.3—XXXX
5除氧器、熱交換器、蒸發器、減壓裝置等的檢查調整;
6各附屬機械分部試運調整;
7潤滑、調節和密封油系統及凈化裝置試運調整,油質合格;
8調節、保安系統靜態整定和試驗;
9頂軸裝置和盤車裝置調整試驗,校對大軸晃度指示表;
10抽汽止回閥與傳動裝置的調整試驗;
11汽封系統調整試運行;
12熱工、電氣有關保護、連鎖裝置,遠方操作裝置和電動、
氣動、液動閥的調整試驗,開、閉、富余行程及開閉時間已作記
錄,并投運正常;
13中間再熱機組旁路系統的調整試驗;
14抽真空試驗;
15低壓缸噴水試驗;
16發電機氫氣冷卻系統、繞組冷卻水系統的沖洗與調整。
11
DL5190.3—XXXX
4汽輪機本體
4.1一般規定
4.1.1本章適用于汽輪機本體的臺板、軸承座、軸承、汽缸、隔
板、汽封、轉子、盤車裝置及連通管道等部件的施工。
4.1.2汽輪機本體的設備吊裝,除應按第3.1
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯系上傳者。文件的所有權益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網頁內容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經權益所有人同意不得將文件中的內容挪作商業或盈利用途。
- 5. 人人文庫網僅提供信息存儲空間,僅對用戶上傳內容的表現方式做保護處理,對用戶上傳分享的文檔內容本身不做任何修改或編輯,并不能對任何下載內容負責。
- 6. 下載文件中如有侵權或不適當內容,請與我們聯系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025隧道襯砌施工合同
- 2025合同解除終止勞動合同證明書
- 2025【IT綜合服務合同】綜合信息服務合同
- 2025年單位貨物運輸合同協議范本模板
- 2024年中國郵政集團有限公司黑龍江省分公司招聘筆試真題
- 2024年六盤水市市屬事業單位考試真題
- 2024年樂昌市市屬事業單位考試真題
- 2024年安慶陽光職業技術學校專任教師招聘真題
- 洗沙加工合同范本
- 鞋業貿易加工合同范本
- 管轄權異議申請書(模板)
- 第十五章藥物制劑的設計
- 人教版高一數學必修一各章節同步練習(含答案)
- 中醫治療“粉刺”醫案16例
- 自動化專業技術總結范文10篇
- 城市消防站建設標準
- 與食品經營相適應的主要設備設施布局、操作流程等文件
- 蘇靈簡要培訓講稿(醫藥代表培訓)
- 陜西省某高速公路工程監理交底材料
- 穿刺術 胸腔穿刺術
- JJG 388-2012測聽設備純音聽力計
評論
0/150
提交評論