文檔簡(jiǎn)介
目錄
第一章施工組織設(shè)計(jì)編制依據(jù)及工程概況...................................................5
第一節(jié)、施工組織設(shè)計(jì)編制說(shuō)明........................................................5
一、編制依據(jù).........................................................................5
二、編制范圍.........................................................................5
三、編制原則.........................................................................5
第二節(jié)工程概況..........................................................................6
一、工程地理位置及主要技術(shù)標(biāo)準(zhǔn)......................................................6
二、工程自然特征.....................................................................6
三、施工條件.........................................................................7
四、主要工程數(shù)量.....................................................................8
五、工程特點(diǎn)分析.....................................................................8
六、施工技術(shù)難點(diǎn)及對(duì)策...............................................................9
第二章設(shè)備、人員安排、動(dòng)員周期和設(shè)備、材料進(jìn)場(chǎng)的方法................................11
第一節(jié)機(jī)械設(shè)備的安排、動(dòng)員周期及調(diào)遣方法........................................11
一、機(jī)械設(shè)備的安排..................................................................11
(一)、主要工程機(jī)械配置........................................................11
(二)、主要試驗(yàn)、測(cè)量、質(zhì)檢儀器配置...........................................11
二、機(jī)械設(shè)備的動(dòng)員周期..............................................................17
三、機(jī)械設(shè)備的調(diào)遣運(yùn)輸方法.........................................................17
第二節(jié)人員的安排、調(diào)遣及任務(wù)劃分.................................................19
一、施工組織管理機(jī)構(gòu)................................................................19
二、項(xiàng)目部主要成員職責(zé)..............................................................22
三、對(duì)人員的素質(zhì)要求及人員的動(dòng)員周期...............................................26
四、勞力組織調(diào)配計(jì)劃及任務(wù)劃分.....................................................26
(一)、人員的計(jì)劃安排..........................................................26
(二)、任務(wù)劃分.................................................................27
第三節(jié)材料組織及供應(yīng)計(jì)劃.........................................................30
一、材料的組織與運(yùn)輸................................................................30
二、主要材料供應(yīng)計(jì)劃................................................................30
三、物資管理體系....................................................................30
第三章施工總體布署...................................................................32
第一節(jié)施工準(zhǔn)備....................................................................32
第二節(jié)臨時(shí)工程施工安排...........................................................32
一、臨時(shí)工程布置原則................................................................32
二、臨時(shí)工程安排..................................................................33
(一)臨時(shí)工程數(shù)量...............................................................33
(二)水電供應(yīng)....................................................................33
(三)臨時(shí)通訊....................................................................34
(四)臨時(shí)房屋....................................................................34
(五)施工便道....................................................................34
(六)混凝土拌合站、預(yù)制場(chǎng)設(shè)置..................................................36
三、臨時(shí)用地計(jì)劃....................................................................36
第四章主要工程項(xiàng)目的施工方案、施工方法...............................................38
第一節(jié)路基及附屬工程施工方案、施工方法..........................................38
一、路基工程概況....................................................................38
二、施工機(jī)具設(shè)備....................................................................38
三、施工方案.........................................................................38
(一)路基土石方調(diào)配............................................................38
(二)施工機(jī)具..................................................................39
(三)施工順序..................................................................39
(四)路基挖方..................................................................39
(五)特殊路基要求..............................................................41
(六)一般路基填筑..............................................................42
(七)清淤換填..................................................................46
(A)路基半挖半填地段填筑.....................................................47
(九)路基修整..................................................................47
(十)防護(hù)工程施工..............................................................48
(十一)排水工程施工............................................................49
第二節(jié)橋梁涵洞工程施工方案.......................................................50
一、橋梁工程施工方案................................................................50
(一)K40+950利民溝中橋........................................................50
1,樁基礎(chǔ)........................................................................50
2、墩臺(tái)身........................................................................58
3、蓋梁(臺(tái)帽).................................................................60
4,20mT梁預(yù)制.................................................................62
5、20mT梁安裝.................................................................66
6、橋面系及附屬工程.............................................................66
(-)K43+539老洪靈溝大橋......................................................66
1、樁基礎(chǔ)........................................................................66
2、承臺(tái)系梁.....................................................................67
3、墩臺(tái)身........................................................................68
4,蓋梁(臺(tái)帽).................................................................68
5、30m、22m箱梁預(yù)制............................................................69
6、30m、22m箱梁安裝............................................................73
7、結(jié)構(gòu)體系轉(zhuǎn)換施工.............................................................77
8、橋面系及附屬工程施工.........................................................78
(三)K45+199分離立交橋........................................................79
1、樁基礎(chǔ)........................................................................79
2、承臺(tái)系梁.....................................................................79
3、墩臺(tái)身........................................................................79
4、蓋梁(臺(tái)帽).................................................................80
5、16m預(yù)應(yīng)力空心板預(yù)制.........................................................80
6、空心板安裝...................................................................83
7、橋面系及附屬工程施工.........................................................84
(四)K46+982分離立交橋........................................................85
1、樁基礎(chǔ)........................................................................85
2、承臺(tái)系梁.....................................................................85
3、墩臺(tái)身........................................................................85
4,蓋梁(臺(tái)帽).................................................................85
5、13m預(yù)應(yīng)力空心板預(yù)制.......................................................85
6、空心板安裝...................................................................85
7、橋面系及附屬工程施工.........................................................86
(五)K49+263分離立交橋........................................................86
1、樁基礎(chǔ)........................................................................86
2、承臺(tái)系梁.....................................................................86
3、墩臺(tái)身........................................................................86
4、蓋梁(臺(tái)帽).................................................................86
5、13m預(yù)應(yīng)力空心板預(yù)制.........................................................87
6、空心板安裝...................................................................87
7、橋面系及附屬工程施工.........................................................87
(六)K50+289.5新灘河大橋....................................................87
1、樁基礎(chǔ)........................................................................87
2、承臺(tái)系梁.....................................................................92
3、墩臺(tái)身......................................................................94
4、蓋梁(臺(tái)帽).................................................................94
5、鋼管混凝土方案..............................................................94
6、30m、25m箱梁預(yù)制..........................................................100
7、30m、25m箱梁安裝..........................................................101
8、結(jié)構(gòu)體系轉(zhuǎn)換施工...........................................................101
9、橋面系及附屬工程施工.......................................................101
(七)K50+750灘河老河道中橋..................................................101
1、樁基礎(chǔ).....................................................................101
2、承臺(tái)系梁...................................................................102
3、墩臺(tái)身......................................................................102
4、蓋梁(臺(tái)帽)................................................................102
5、16m預(yù)應(yīng)力空心板預(yù)制.......................................................102
6、空心板安裝.................................................................102
7、橋面系及附屬工程施工.......................................................1。2
(八)K51+208分離立交橋.......................................................102
1,樁基礎(chǔ)......................................................................102
2、承臺(tái)系梁...................................................................103
3、墩臺(tái)身......................................................................103
4,蓋梁(臺(tái)帽)...............................................................103
5、13m預(yù)應(yīng)力空心板預(yù)制.......................................................103
6、空心板安裝.................................................................103
7、橋面系及附屬工程施工.......................................................1。4
(九)三座車(chē)行天橋............................................................104
1、樁基施工...................................................................104
2、墩臺(tái)身施工.................................................................104
3、臺(tái)帽施工...................................................................104
4,支架基礎(chǔ)...................................................................104
5、滿(mǎn)堂支架搭設(shè)及荷載預(yù)壓.....................................................104
6、模板結(jié)構(gòu)及支撐體系.........................................................106
7、槽型梁鋼筋加工及安裝.......................................................106
8、混凝土施工.................................................................106
9、預(yù)應(yīng)力施工.................................................................107
10、支架的拆除................................................................111
二、圓管涵施工方案.................................................................112
三、裝配式涵洞、蓋板通道、蓋板涵施工方案.........................................115
第六章冬季、雨季和農(nóng)忙季節(jié)施工安排..................................................125
一、冬季施工措施...................................................................125
(一)鋼筋工程.................................................................125
(-)模板工程.................................................................125
(三)混凝土工程...............................................................125
二、雨季施工措施...................................................................126
三、農(nóng)忙季節(jié)施工安排...............................................................126
第七章工期、質(zhì)量、安全、環(huán)保和節(jié)能措施.............................................128
一、工期保證措施...................................................................128
二、質(zhì)量保證措施...................................................................129
(一)質(zhì)量保證體系、質(zhì)量責(zé)任制及具體措施.....................................129
(-)建立質(zhì)量信息反饋系統(tǒng).....................................................129
(三)運(yùn)用QC管理和IS09001管理體制.........................................129
(四)正確處理進(jìn)度與質(zhì)量的關(guān)系................................................129
(五)質(zhì)量保證體系.............................................................130
1、組織保證....................................................................132
2、制度保證....................................................................132
三、安全保證措施...................................................................132
(一)安全生產(chǎn)管理的基本方針..................................................132
(二)安全生產(chǎn)管理體系和責(zé)任制................................................132
(三)安全技術(shù)措施制度.........................................................134
(四)安全教育與培訓(xùn)...........................................................135
四、環(huán)保、節(jié)能措施.................................................................136
(一)環(huán)境保護(hù)保證措施.........................................................136
(二)文明施工措施.............................................................136
五、各項(xiàng)安全生產(chǎn)事故應(yīng)急...........................................................136
(一)編制目的.................................................................136
(二)編制依據(jù).................................................................137
(三)運(yùn)用范圍.................................................................137
(四)應(yīng)急救援指揮協(xié)調(diào)機(jī)構(gòu)....................................................137
(五)職責(zé)分工.................................................................137
(六)應(yīng)急救援原則.............................................................138
(七)應(yīng)急救援的演練...........................................................138
(A)救援物資.................................................................138
(九)各小組成員聯(lián)系方式......................................................139
(+)應(yīng)急預(yù)案的評(píng)價(jià)與更新....................................................139
第八章項(xiàng)目管理新思路、新辦法.........................................................154
一、量化承包........................................................................154
二、工作流程化.....................................................................154
三、首件認(rèn)可制......................................................................154
第九章施工成本預(yù)測(cè)及控制辦法,效益預(yù)估.............................................155
一、建立項(xiàng)目成本責(zé)任制,完善項(xiàng)目成本控制運(yùn)行機(jī)制.................................155
二、將成本管理貫穿于工程項(xiàng)目實(shí)施的全過(guò)程..........................................155
第十章廉政建設(shè)保證措施...............................................................158
附件:
主要分項(xiàng)工程工藝流程圖
徐明04標(biāo)車(chē)行天橋現(xiàn)澆箱梁支架布置圖
施工總體平面布置圖
拌和站、預(yù)制場(chǎng)總體平面布置圖
施工總體計(jì)劃表
施工總體施工斜率圖
施工總體計(jì)劃網(wǎng)絡(luò)圖
分項(xiàng)工程生產(chǎn)率和施工周期表
工程管理曲線(xiàn)
勞動(dòng)力用計(jì)劃圖
資金使用計(jì)劃圖
第一章施組編制依據(jù)及工程概況
第一節(jié)施工組織設(shè)計(jì)編制說(shuō)明
一、編制依據(jù)
1、徐明高速公路路基工程XMLJ-04合同段合同協(xié)議書(shū)、招標(biāo)文件。
2、安徽省交通規(guī)劃設(shè)計(jì)研究院有限公司提供的《兩階段施工圖設(shè)計(jì)文件》及其它設(shè)
計(jì)資料。
3、交通部頒發(fā)的現(xiàn)行規(guī)范、規(guī)程、規(guī)則、檢驗(yàn)評(píng)定標(biāo)準(zhǔn)、公路工程施工定額、概預(yù)
算編制辦法。
4、現(xiàn)場(chǎng)踏勘調(diào)查所獲得的有關(guān)資料。
5、我單位擁有的科技工法成果和現(xiàn)有的管理水平、勞力設(shè)備、技術(shù)能力,以及長(zhǎng)期
從事高速公路建設(shè)所積累的豐富的施工經(jīng)驗(yàn)。
二、編制范圍
徐州至明光高速公路路基工程第四合同段,即設(shè)計(jì)里程K40+905-K52+175全長(zhǎng)
1L27公里范圍內(nèi)的路基工程、橋涵工程、排水防護(hù)的施工及保修。
三、編制原則
1、嚴(yán)格執(zhí)行國(guó)家、有關(guān)各部及省市基本建設(shè)的政策、法令、法規(guī)、施工技術(shù)規(guī)范、
操作規(guī)程、質(zhì)量評(píng)定標(biāo)準(zhǔn)等。
2、嚴(yán)格遵守合同條款以及招標(biāo)文件的各項(xiàng)要求,根據(jù)工程的特點(diǎn)和輕重緩急,分期
分批組織施工。
3、堅(jiān)持在實(shí)事求是的基礎(chǔ)上,力求技術(shù)先進(jìn)、科學(xué)合理、經(jīng)濟(jì)適用的原則.在確保
工程質(zhì)量的前提下,積極采用新技術(shù)、新工藝、新材料。
4、合理安排施工的程序和順序,做到布局合理,突出重點(diǎn)、全面展開(kāi)、平行流水作
業(yè),正確選用施工方法,科學(xué)組織,均衡生產(chǎn)。各工序緊密銜接,避免不必要的重復(fù)工作,
以保證施工連續(xù)均衡有序進(jìn)行。
5、施工進(jìn)度安排考慮各分項(xiàng)工程間的協(xié)調(diào)和配合,并充分考慮氣候、季節(jié)對(duì)施工的
影響。
6、結(jié)合現(xiàn)場(chǎng)實(shí)際情況,因時(shí)因地制宜,盡量利用原有設(shè)施或就近已有的設(shè)施,減少
各種臨時(shí)工程,盡量利用當(dāng)?shù)睾细褓Y源,合理安排運(yùn)輸、裝卸與儲(chǔ)存作業(yè),減少物資運(yùn)輸
周轉(zhuǎn)工作量。
7、堅(jiān)持自始至終對(duì)施工現(xiàn)場(chǎng)全過(guò)程嚴(yán)密監(jiān)控,以科學(xué)的方法實(shí)行動(dòng)態(tài)管理,并按動(dòng)
靜結(jié)合的原則,精心進(jìn)行施工場(chǎng)地規(guī)劃布置,節(jié)約施工臨時(shí)用地,不占或少占農(nóng)田,不破
壞植被。嚴(yán)格組織、精心管理,文明施工,創(chuàng)標(biāo)準(zhǔn)化施工工地。
8、嚴(yán)格執(zhí)行交通部頒發(fā)現(xiàn)行的和招標(biāo)文件明確的設(shè)計(jì)規(guī)范、施工規(guī)范及驗(yàn)收標(biāo)準(zhǔn)
9、加強(qiáng)工程進(jìn)度的科學(xué)性、計(jì)劃性管理,合理安排機(jī)械、材料、勞動(dòng)力的進(jìn)退場(chǎng),
確保現(xiàn)場(chǎng)文明整潔。
10、遵循國(guó)家及當(dāng)?shù)卣嘘P(guān)環(huán)保文件精神,采取有效措施,減少環(huán)境污染,降低噪
音。
第二節(jié)工程概況
一、工程地理位置及主要技術(shù)標(biāo)準(zhǔn)
徐州至明光高速公路是安徽“四縱八橫”高速公路網(wǎng)中“縱一”部分,已被列入交通
部《促進(jìn)中部地區(qū)崛起公路水路交通發(fā)展規(guī)劃綱要》,項(xiàng)目的建設(shè)將構(gòu)筑又一條連接山東、
蘇北、皖東北地區(qū)與長(zhǎng)江三角地區(qū)的便捷通道,有利于加強(qiáng)中部欠發(fā)達(dá)省市與東部沿海發(fā)
達(dá)地區(qū)、特別是長(zhǎng)三角經(jīng)濟(jì)圈的經(jīng)濟(jì)聯(lián)系,促進(jìn)中部地區(qū)的資源優(yōu)勢(shì)轉(zhuǎn)化成經(jīng)濟(jì)優(yōu)勢(shì),縮
小區(qū)域經(jīng)濟(jì)差距,對(duì)促進(jìn)中部地區(qū)崛起、實(shí)施安徽省東向發(fā)展戰(zhàn)略、加速融入長(zhǎng)三角、構(gòu)
筑和諧社會(huì)、全面建設(shè)小康社會(huì)等具有重要意義和作用。
徐州至明光公路起點(diǎn)接徐州至明光高速公路江蘇段,省界接點(diǎn)位于梁莊(屬安徽)的
西北角,前焦?fàn)I(屬江蘇)的南部,接點(diǎn)樁號(hào)(即本項(xiàng)目起點(diǎn))K3+200。路線(xiàn)終點(diǎn)在明西
街道附近接明光至蚌埠高速公路,路線(xiàn)終點(diǎn)樁號(hào)YK142+232.193(明光樞紐互通右線(xiàn)終
點(diǎn))。路線(xiàn)全長(zhǎng)139.06公里。
本標(biāo)段樁號(hào)為K40+905至K52+175,起點(diǎn)位于靈璧縣馮廟鎮(zhèn)南利民溝北岸,經(jīng)泗縣楊
集鎮(zhèn),終點(diǎn)位于泗縣長(zhǎng)溝鎮(zhèn),沿線(xiàn)跨越利民溝(中橋)、老洪靈溝(大橋)、新灘河(大橋)、
老灘河(中橋),本標(biāo)段全長(zhǎng)1L27公里。
本標(biāo)段為雙向四車(chē)道高速公路標(biāo)準(zhǔn),路基寬度27m,路基橫斷面幾何尺寸布置為:0.75
米(土路肩)+3.50米(硬路肩)+2x3.75米(行車(chē)道)+0.75米(路緣帶)+2.0米(中
央分隔帶)+0.75米(路緣帶)+2x3.75米(行車(chē)道)+3.50米(硬路肩)+0.75米(土
路肩),設(shè)計(jì)行車(chē)速度:120Km/h。全線(xiàn)設(shè)計(jì)汽車(chē)荷載標(biāo)準(zhǔn):公路-I級(jí),設(shè)計(jì)洪水頻率:
特大橋1/300,路基、大、中、小橋涵1/100。平曲線(xiàn)最小半徑3300m,縱斷面最大縱坡
1.9%。
二、工程自然特征
1.地形與地貌概況
本項(xiàng)目位于安徽省東北部,地跨淮河兩岸,全線(xiàn)地形地貌以淮河為界分為淮北平原和
江淮丘陵,沿線(xiàn)大型河流較多、人工溝渠眾多。淮北平原北部零星分布著低丘,其余大部
分為廣闊平原,地面十分平坦,與已建的泗宿高速公路地形條件類(lèi)似。江淮波狀平原丘崗
起伏,低丘散布于區(qū)內(nèi),與已建的明蚌高速公路地形條件類(lèi)似。
2.氣象與水文概況
沿線(xiàn)地形、地質(zhì)、地震、氣候、水文等自然地理特征及其與公路建設(shè)的關(guān)系
2-1區(qū)域地質(zhì)條件
項(xiàng)目區(qū)地層區(qū)劃屬華北地層區(qū)淮河地層分區(qū),地層發(fā)育不全,分布的地層有上太古界、
震旦系及侏羅系、白堊系、第三系。上太古界五河群(Ar2wh)分布于項(xiàng)目區(qū)的南部,震
旦系分布于項(xiàng)目區(qū)的北部,侏羅系、白堊系、第三系主要分布于項(xiàng)目區(qū)的中部、南部。項(xiàng)
目區(qū)前第四系除少部分出露于低丘外,絕大部分伏于第四系之下。項(xiàng)目區(qū)第四紀(jì)地層大致
以淮河為界,分屬宿縣一阜陽(yáng)地層小區(qū)和嘉山一六安地層小區(qū),兩地層小區(qū)的第四紀(jì)厚度、
巖性差異較大。
工程沿線(xiàn)跨中朝準(zhǔn)地臺(tái)淮河臺(tái)坳的淮北陷褶帶蚌埠臺(tái)拱。淮北陷褶斷帶位于淮河臺(tái)坳
的北部,可細(xì)分為亳縣穹褶束、宿州凹斷褶束、靈璧臺(tái)穹構(gòu)造單元,項(xiàng)目區(qū)位于靈璧臺(tái)穹
構(gòu)造單元。線(xiàn)路經(jīng)過(guò)該構(gòu)造單元內(nèi)的褶皴有:九頂山復(fù)式向斜的九頂山向斜、周玨背斜,
高集復(fù)式背斜的大馬家向斜、高集背斜。項(xiàng)目選線(xiàn)區(qū)域分布的深、大斷裂有:宿(州)北
斷裂、泗縣斷裂、利辛斷裂、鄭廬斷裂帶,其中鄭廬斷裂帶屬活動(dòng)斷裂。
2-2水文地質(zhì)評(píng)價(jià)
項(xiàng)目區(qū)大致以淮河為界,分為淮北平原水文地質(zhì)區(qū)和江淮波狀平原水文地質(zhì)區(qū)。
淮北平原水文地質(zhì)區(qū),與本工程建設(shè)關(guān)系密切的為松散巖類(lèi)孔隙水和碳酸鹽巖裂隙溶洞
水。江淮波狀平原水文地質(zhì)區(qū),本區(qū)地下水類(lèi)型為松散巖類(lèi)孔隙水、基巖裂隙水和紅層孔
隙裂隙水。
2-3氣候
項(xiàng)目區(qū)氣候特征:氣候溫和、四季分明、雨量適中、光照充足,無(wú)霜期較長(zhǎng),光、
熱、水資源都比較豐富,具明顯的過(guò)渡性特征,大致以淮河為界,淮河以北為暖溫帶半濕
潤(rùn)季風(fēng)氣候,淮河以南為亞熱帶濕潤(rùn)季風(fēng)氣候。氣候的過(guò)渡性及變異性,也常常帶來(lái)旱澇、
連陰雨、低溫、霜凍等氣候?yàn)?zāi)害.年平均氣溫14.0~16.1。C極端最高氣溫41.3。C,年
極端最低氣溫-22.8。Co多年平均降水量872.9~903.2mm,年最大降水量為1559mm,年最
小降水量為442mm。降水年內(nèi)分布不均,6至9月降水量較大,11月至次年2月降水量最
小。多年平均蒸發(fā)量1421.9~1651mm,相對(duì)濕度為72~77%.全年主導(dǎo)風(fēng)向,春夏多東及東
南風(fēng),秋冬多西北及北風(fēng),風(fēng)速極大風(fēng)速大于40m/s.
2-4自然區(qū)劃
根據(jù)部頒公路自然區(qū)劃標(biāo)準(zhǔn)》(JTJ003—86),本項(xiàng)目淮河以北屬H5區(qū),淮河
以南屬I(mǎi)V2區(qū)。
三、施工條件
本項(xiàng)目沿線(xiàn)路網(wǎng)頒布較發(fā)達(dá),區(qū)域內(nèi)以國(guó)道G104作為主要干路,沿線(xiàn)分布有多條省、
縣、鄉(xiāng)公路,形成區(qū)域交通主網(wǎng)絡(luò)。主要公路有:國(guó)道104、省道S302、S303o鐵路有宿
淮鐵路。
1、主要河流
大型河流主要有:利民溝、老洪靈溝、新灘河、老灘河等。
2、沿線(xiàn)筑路材料、水、電等建設(shè)條件
土:淮河以多為旱地,工程用土可采用路側(cè)集中取土方式。淮河以南路線(xiàn)穿越江淮丘
陵區(qū),沿線(xiàn)地下水位較低,利用崗地取土。
石料:靈璧縣三山石料場(chǎng)、泗縣老山石料場(chǎng),主產(chǎn)石灰?guī)r,可用于路基工程。
砂:公路用砂可取自明光池河、江蘇新沂、江蘇灘寧。
石灰:符離集橫口石灰廠(chǎng)位于符離集北側(cè),產(chǎn)品質(zhì)量穩(wěn)定合格,原料就地取材。另外,
滁州市鳳陽(yáng)也有石灰廠(chǎng),產(chǎn)量豐富、質(zhì)量?jī)?yōu)良,施工時(shí)可供選用。
木材:從項(xiàng)目沿線(xiàn)各市、縣木材市場(chǎng)購(gòu)買(mǎi)。
工程用水用電:項(xiàng)目所經(jīng)地區(qū)河渠密布,公路建設(shè)用水便利。工程用電與沿線(xiàn)地方電
力部門(mén)協(xié)商,就近解決,并應(yīng)考慮自配發(fā)電機(jī),以備急用。
本項(xiàng)目區(qū)域內(nèi)有國(guó)道104、省道S302、S303等,汽車(chē)運(yùn)輸作為材料的主要運(yùn)輸手段
但臨近工地的縣鄉(xiāng)道路正在修建影響運(yùn)輸;總體來(lái)講,本項(xiàng)目區(qū)域交通運(yùn)輸條件十分困難。
四、主要工程數(shù)量
序
號(hào)項(xiàng)目名稱(chēng)單位數(shù)量備注
1路線(xiàn)長(zhǎng)度公里11.27
清表平方米382746
土石方填方立方米1272272.06
2
工程挖方立方米13171.06
挖淤泥立方米14661
漿砌片石立方米13491
排水防
3混凝土立方4449.4
護(hù)數(shù)量
排水溝米20673
橋
涵橋梁長(zhǎng)度米/座1267.12/11
4特大橋米/座
大橋米/座750/2
橋
涵中橋米/座136.12/2
4小橋米/座
“涵洞延米/道1315.16/37
跖
線(xiàn)互通立交米/座
交分離立交米/座165/4
5叉
通道延米/道689.1/23
天橋米/座216/3
五、工程特點(diǎn)分析
經(jīng)現(xiàn)場(chǎng)實(shí)地考察、仔細(xì)閱讀《兩階段施工圖設(shè)計(jì)文件》后,歸納起來(lái)本項(xiàng)目工程有如
下幾個(gè)特點(diǎn):
1.工程項(xiàng)目種類(lèi)多:本合同段線(xiàn)路長(zhǎng)度為11.27km,橋、涵、路基土石方、各類(lèi)支
擋、防護(hù)等項(xiàng)目齊全,其中路基挖土方3206m\填1272272.06m)橋梁合計(jì)1267.
座。
2.重點(diǎn)、難點(diǎn)突出、施工技術(shù)要求標(biāo)準(zhǔn)高:K50+289.500新灘河大橋采用60米下承
式桁架梁+P.C.小箱梁。橋梁上部下弦桿、橋面板、中橫梁和端橫梁采用滿(mǎn)堂支架施工,7~
9跨樁基為水中樁。如何合理安排工期,成功避開(kāi)洪水期,保證下部基礎(chǔ)的工程質(zhì)量成為
本合同段的一道難題;本橋采用單跨60m下承的鋼管混凝土桁架組合梁橋方案,為國(guó)內(nèi)外
首次采用的結(jié)構(gòu),是本合同段質(zhì)量控制的又一難點(diǎn)。
3.項(xiàng)目區(qū)地形復(fù)雜,文明施工、環(huán)境保護(hù)、水土保持任務(wù)重:施工中要合理布置場(chǎng)
地和修建便道,充分利用每一塊地方,盡量少占農(nóng)田。同時(shí),本合同段路基填方量大,需
挖取土坑多且面積大,必須作好施工時(shí)的環(huán)境保護(hù)工作,堅(jiān)持文明施工,減少植被破壞,
控制水土流失和污染,最大限度控制對(duì)周邊環(huán)境的影響。本工程項(xiàng)目在7~9月降雨量較
大,施工期間需特別注意防洪、防澇、防汛等安全渡汛工作,確保洪澇、大風(fēng)季節(jié)不受或
少受損害,確保洪澇、大風(fēng)季節(jié)的工程質(zhì)量及材料儲(chǔ)備,盡量保證洪澇、大風(fēng)季節(jié)能正常
施工,尤其是取土坑設(shè)計(jì)挖深為5m,地下水位高施工過(guò)程中蓄水深,沿線(xiàn)居民多,存在極
大的安全隱患,需加強(qiáng)做好安全防護(hù)。
4.工期緊、任務(wù)重、安全要求高:根據(jù)業(yè)主要求,路基、橋涵工期18個(gè)月,經(jīng)一個(gè)
冬季和春節(jié),工期十分緊張。橋梁水中樁立柱、梁體架設(shè)施工,對(duì)安全要求高;在施工過(guò)
程中,要針對(duì)各分項(xiàng)工程特點(diǎn),制定相應(yīng)的安全保證措施。
5.材料進(jìn)場(chǎng)道路不便:由于本合同段所屬區(qū)域內(nèi)正在進(jìn)行縣路網(wǎng)混凝土路面改造,
在整個(gè)施工期間材料進(jìn)場(chǎng)都將嚴(yán)重受到嚴(yán)重影響。
6.當(dāng)?shù)赝ㄐ拧㈦娏^為發(fā)達(dá);并且沿線(xiàn)水系發(fā)達(dá),用水方便,給施工帶來(lái)方便。
六、施工技術(shù)難點(diǎn)及對(duì)策
通過(guò)分析,本合同段施工的主要難點(diǎn)是鋼管混凝土桁架橋施工;其次是水中樁、系梁、
立柱施工,具體分析及擬采取的對(duì)策如下所述。
1.鋼管混凝土桁架橋施工
(1)認(rèn)真分析項(xiàng)目施工特點(diǎn),根據(jù)設(shè)計(jì)文件和現(xiàn)場(chǎng)施工的實(shí)際情況,采取積極有效的
措施,確保鋼管混凝土桁架橋施工的順利進(jìn)行。
(2)首先是我部施工便道的暢通,其次是鋼材的選定。
(3)采用先進(jìn)的機(jī)械進(jìn)行安裝施工,確保施工安全。
(4)因?yàn)殇摴芑炷凌旒軜蛄菏菄?guó)內(nèi)首例,施工工藝將是我部施工的難點(diǎn)。
2.水中樁、系梁、立柱施工
加強(qiáng)施工時(shí)的地質(zhì)和水汶觀(guān)察工作,樁基施工采用鋼護(hù)筒施工,系梁采用鋼圍堰或鋼
套箱,加強(qiáng)觀(guān)測(cè)和信息反饋,堅(jiān)持動(dòng)態(tài)觀(guān)測(cè)、動(dòng)態(tài)施工,確保施工安全,做到一次成功,
不留后患,具體抓好以下幾點(diǎn):
(1)做好鉆機(jī)平臺(tái)和施工平臺(tái)搭設(shè)。
(2)加強(qiáng)高鋼護(hù)筒施工的穩(wěn)固工作:
一是在下護(hù)筒前做好護(hù)筒的加固;
二是做好施工過(guò)程中的排水。
(3)合理安排水中樁施工順序。
(4)采取雨季避讓的措施,降低施工難度。
(5)堅(jiān)持動(dòng)態(tài)監(jiān)測(cè)、動(dòng)態(tài)施工原則,加強(qiáng)監(jiān)測(cè),并及時(shí)進(jìn)行信息反饋,以指導(dǎo)施工。
(6)選用經(jīng)驗(yàn)豐富、有資質(zhì)的專(zhuān)業(yè)隊(duì)進(jìn)行施工;成立水中樁施工技術(shù)管理領(lǐng)導(dǎo)小組,
以項(xiàng)目總工為組長(zhǎng),結(jié)構(gòu)工程師和質(zhì)檢工程師為副組長(zhǎng),專(zhuān)項(xiàng)進(jìn)行施工管理和技術(shù)指
第二章設(shè)備、人員安排、動(dòng)員周期
和設(shè)備、材料進(jìn)場(chǎng)的方法
第一節(jié)機(jī)械設(shè)備的安排、動(dòng)員周期及調(diào)遣方法
一、機(jī)械設(shè)備的安排
(一)、主要工程機(jī)械配置
機(jī)械設(shè)備圍繞土方挖、裝、運(yùn)、推、平、拌灰、壓采用全機(jī)械化作業(yè);混凝土均采用
拌合站集中生產(chǎn),混凝土罐車(chē)運(yùn)輸、輸送泵灌注;橋梁預(yù)應(yīng)力空心板梁、箱梁在預(yù)制場(chǎng)集
中預(yù)制、采用架橋機(jī)和吊車(chē)架設(shè)。
設(shè)備配置情況見(jiàn)《擬投入本合同工程的隊(duì)伍及主要施工機(jī)械》。
(二)、主要試驗(yàn)、測(cè)量、質(zhì)檢儀器配置
建立工地試驗(yàn)室,解決施工中常規(guī)試驗(yàn)和檢測(cè)問(wèn)題,主要試驗(yàn)、測(cè)量、質(zhì)檢儀器見(jiàn)《擬
投入本合同工程的試驗(yàn)儀器設(shè)備表》。
投入本合同工程的主要試驗(yàn)儀器設(shè)備表
序號(hào)設(shè)備名稱(chēng)廠(chǎng)牌及規(guī)格型號(hào)精度量程數(shù)量性能狀況購(gòu)買(mǎi)日期備注
1電子天平JF2000.110001合格新購(gòu)
2臺(tái)秤TGT-1001三級(jí)合格新購(gòu)
3電熱恒溫干燥箱101A-41良好新購(gòu)
4石灰土試驗(yàn)儀5KN1良好新購(gòu)
5承載比試驗(yàn)儀30K1合格新購(gòu)
6混凝土回彈儀ZC3-A1合格新購(gòu)
7游標(biāo)卡尺0-150mm1合格新購(gòu)
8混凝土振動(dòng)臺(tái)1.1m21良好新購(gòu)
9水泥細(xì)度負(fù)壓篩析儀FSY-150B1合格新購(gòu)
10萬(wàn)能試驗(yàn)機(jī)WES-1000B11.0級(jí)新購(gòu)
11壓力試驗(yàn)機(jī)DYE-200011.0級(jí)新購(gòu)
12水泥膠砂攪拌機(jī)JJ-51良好新購(gòu)
13水泥碎
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶(hù)所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶(hù)上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶(hù)上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶(hù)因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 沙灣縣2025年六年級(jí)下學(xué)期小升初招生數(shù)學(xué)試卷含解析
- 上海市浦東新區(qū)2025年小升初數(shù)學(xué)模擬試卷含解析
- 南通職業(yè)大學(xué)《園林生態(tài)學(xué)》2023-2024學(xué)年第二學(xué)期期末試卷
- 江蘇省揚(yáng)州市江都區(qū)八校2025年初三下學(xué)期階段測(cè)試(二)英語(yǔ)試題試卷含答案
- 貴州機(jī)電職業(yè)技術(shù)學(xué)院《系統(tǒng)工程基礎(chǔ)》2023-2024學(xué)年第一學(xué)期期末試卷
- 山西省三區(qū)八校2025年高三下學(xué)期第三次診斷考試物理試題含解析
- 2025年山東省濟(jì)南市山東師范大學(xué)附中高三第二學(xué)期開(kāi)學(xué)統(tǒng)練數(shù)學(xué)試題含解析
- 2025年貴州省黔南州第二學(xué)期期末教學(xué)質(zhì)量檢測(cè)試題初三化學(xué)試題含解析
- 云南省保山市隆陽(yáng)區(qū)保山曙光學(xué)校2025屆數(shù)學(xué)五下期末監(jiān)測(cè)模擬試題含答案
- 2022抖音知識(shí)課件
- 軍事國(guó)防教育基地方案
- 金氏五行升降中醫(yī)方集
- 小兒常見(jiàn)皮疹識(shí)別與護(hù)理
- 2025年山西經(jīng)貿(mào)職業(yè)學(xué)院?jiǎn)握新殬I(yè)技能考試題庫(kù)新版
- 某連鎖藥店公司發(fā)展戰(zhàn)略
- 2025年河南工業(yè)和信息化職業(yè)學(xué)院?jiǎn)握新殬I(yè)技能測(cè)試題庫(kù)及答案1套
- 校長(zhǎng)在2025春季開(kāi)學(xué)思政第一課講話(huà):用《哪吒2》如何講好思政課
- 《迪拜帆船酒店》課件
- 2025年晉城職業(yè)技術(shù)學(xué)院高職單招語(yǔ)文2018-2024歷年參考題庫(kù)頻考點(diǎn)含答案解析
- (一模)烏魯木齊地區(qū)2025年高三年級(jí)第一次質(zhì)量歷史試卷(含官方答案)
- 《漂亮的熱帶魚(yú)》課件
評(píng)論
0/150
提交評(píng)論