1SiteReportofAuchanNingboXinxingPhaseII寧波新星二期項目現場報告23EastFacade東立面4SouthFacade南立面5NorthFacade北立面6ConnectionbetweenPhaseI&PhaseII一期、二期結合處B2地下二層Floorpouring地坪澆筑B1地下一層B1地下一層Wallplastering墻面抹灰B1地下一層FreezerRoom冷凍機房1F地上一層2F地上二層3F地上三層3F地上三層Exquisitemodelarea精裝修樣板區Roof屋面Rooftrussinstallation屋面大網架安裝Lightingglasswindowinstallation采光天窗玻璃安裝Outside室外RoadConstruction道路施工Outside室外Aluminuminstallation鋁板安裝Outside室外TheALCboardisongoing.ALC板安裝Outside室外Cranedismantling塔吊拆除SanbaoProject三寶項目Sanbaoprojectiscurrentlyintheshutdown.三寶項目目前處于停工狀態。24Mainstructurecompleted
100%主體結構完成100%Steelstructureworkcompleted100%
鋼結構完成100%Wallmasonrycompleted100%砌體完成100%Exquisitecompleted10%精裝修完成10%Outsideworkcompleted55%
室外工程完成55%M&Eworkcompleted87%
機電完成87%FFSworkcompleted70%消防完成70%Curtainworkcompleted60%
幕墻完成60%PhaseIIConstructionSchedule二期工程進度25Mainstructurecompleteon28thSeptember2013
2013年9月28日主體結構完成Steelstructurecompleteon10thDecember2013
2013年12月10日鋼結構完成ForFFAcceptance,waitingforDAItoconfirmthepowerequipmentsupplyandPowerBureautoconfirmthedateofformalpowersupplyopening.
關于消防驗收,等待非直采確認供電設備的供應以及供電局確認正式用電的開通日期。PhaseIIConstructionSchedule二期工程進度26PowerBureaurequireAuchantoberesponsibleforpowerpipetrenchwhichisoutofAuchanredline.Expansiondepartmentiscurrentlyoncoordinationwithgovernment.Weestimatetheopeningofformalpowersupplywillbedelayedto30thApril2014.
供電局要求歐尚負責建設歐尚紅線外的電纜管溝。發展部正在與政府協商。我們估計正式供電要延期至2014年4月30日開通。AboutUtility關于市政配套Inthisyear,20meetingshasbeenheldamongtechnical,construction,gallerydepartment(on01/14、02/02、03/07、03/22、03/28、03/29、04/17、05/14、05/21、05/31、06/11、06/21、07/12、07/16、07/24、07/31、08/28、09/12、09/13、09/26),discussingallthemattersneededtobeconfirmedbygallery.Sofar,still7notconfirmed,pleaseseethelistmemobelow.今年,技術部、工程部、招商部門共同召開了20次的會議(分別在01/14、02/02、03/07、03/22、03/28、03/29、04/17、05/14、05/21、05/31、06/11、06/21、07/12、07/16、07/24、07/31、08/28、09/12、09/13、09/26),討論了所有需要招商部門確認的事宜。截止目前,還有7條沒有得到確認,詳見后面的清單。AboutGallery關于招商Tobeconfirmed1/4ItemDescriptionsActionPlanresponsiblePartySchedulepriorityDeadlineRemarkImpact1confirmationforcommerciallayoutUpdatedDetaileddesignbaseonthefinallayoutGalleryTechnical2013/1/15-2013/1/23125-Jan-13Finishedonthe25thMarch2013
2PowercapacityfortenantsconfirmationUpdatedDetaileddesignGallery2013/1/15-2013/1/23125-Jan-13Finishedonthe25thMarch2013Constructiondrawing3monthdelayed3DesignSpec/parameter/interfaceconfirmationneedtobeincludedindetaileddesignGallery2013/1/25-2013/2/528-Feb-13Finishedonthe25thMarch2013Constructiondrawing3monthdelayed4ShoppingmallOperationandpropertymanagementrequirementsOperationandmanagementfacilitiesrequirementstobeinputintothedesignGallery2013/2/15-2013/4/20125-Mar-13Designconditionsandreservationneedtobeconfirmedbefore2013/1/31Constructiondrawingdelay5ITandmunicationfortenantsSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13mechanicalroomreservedConstructiondrawingdelay6BuildingAutomaticManagementsystemSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13mechanicalroomreservedConstructiondrawingdelay7SecurityandaccesscontrolsystemSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13mechanicalroomreservedConstructiondrawingdelay8PublicaddresssystemSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13mechanicalroomreservedConstructiondrawingdelayColorinyellowmeansdelayTobeconfirmed2/4ItemDescriptionsActionPlanresponsiblePartySchedulepriorityDeadlineRemarkImpact9CATVforpublicandtenantsSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13NotconsiderednowConstructiondrawingdelay10Wi-FiandWirelesscoverageSystemscheme/scope/functionspecGallery2013/3/15-2013/4/3111-Jun-13
11gasneedsandapplicationforTenantsconfirmationengagethedetaileddesignerGallery2013/3/1-2013/3/31125-Apr-13Total600M/hourreservedat20130202
12ShoppingMallinformation/communicationinteractsystemneedspecificstudyanddesignwithneedsconfirmedGallery2013/3/15-2013/4/311-Jun-13
13SMcustomerflowcalculationSystemneedspecificstudyanddesignwithneedsconfirmedGallery2013/3/15-2013/4/321-Jun-13
14ParkingmanagementsystemneedspecificstudyanddesignwithneedsconfirmedGallery2013/4/15-2013/5/3021-Jul-13
15TenantsconstructionmanagementandcommonzoneoperationprotocolandinterfacedetailedmanagementapproachmustbedefinedbeforeinteriorworkstartGallery2013/5/15-2013/7/30225-Sep-13
16TenantsconstructionpermitsdetailedmanagementapproachmustbedefinedbeforeinteriorworkstartGallery2013/7/15-2013/8/30225-Sep-13
ColorinyellowmeansdelayTobeconfirmed3/4ItemDescriptionsActionPlanresponsiblePartySchedulepriorityDeadlineRemarkImpact17TenantsopeningconditionsbySMdetailedmanagementapproachmustbedefinedbeforeinteriorworkstartGallery2013/7/15-2013/8/30225-Sep-13
18TrolleyflowlimitationdesignforthespaceandfacilitiesofthebarriersGallery2013/1/15-2013/1/23325-Jan-13
19SMStaffparking&accesscontrolneedindependsignandinputtoSecuritiessystemGallery2013/3/15-2013/4/3141-Jun-13Finishedonthe25thMarch2013Constructiondrawing3monthdelayed20stormwaterrecyclingReviewandconfirmtheproposalUMAN2013/3/15-2013/4/31415-May-13ProponedM&EDesignDelay21CoolingcapacityfortenantsconfirmationUpdatedDetaileddesignGallery2013/3/1-2013/3/20125-Jan-13Finishedonthe25thMarch2013MEPConstructiondrawingdesign22Landscape/Sign/LogodesignconfirmationCurtainwallDetaileddesignbaseontheSign/LogodesignconfirmationGallery2013/1/15-2013/3/20130-Apr-13
impacttheprogressofBMdesign23TenantssetbacktoCurtainwallinsidespacetoensuretheimageofentirefacadeGallery2013/7/201-2013/731431-Aug-13
24TenantsmoveinconditionsandscheduleNeedcommonunderstandingforthetenantsmoveinbeforeFFinspectionandtheconstructioncompletiondateGalleryTechnicalConstruction2013/5/15-2013/6/10120-Jun-13Itisnotsameunderstandingwithconstructiondepartmentimpactentireprojecttargetscheduleandsiteconstructionorganization.Tobeconfirmed4/4ItemDescriptionsActionPlanresponsiblePartySchedulepriorityDeadlineRemarkImpact25Tenantsdesignandconstructionmanagementplan&protocolfurtherclarificationneedfromthemanagementtoplanworkingscheduleGalleryTechnicalConstructionUMAN2013/5/15-2013/6/20225-Jun-13
26RequestofB1commercialUpdatedDetaileddesignGallery
TechnicalASAP120-Apr-13
27TheBridgeconnectionwithSanbao
ExpansionGallery
Technical2013/4/15-2013/5/1511-Jun-13pending
28FreshairandventilationofKitchenUpdatedDetaileddesignGallery2013/5/17-2013/5/31130-May-1329locationofthewastewaterofeachtenantUpdatedDetaileddesignGallery2013/5/17-2013/5/31130-May-13
30
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯系上傳者。文件的所有權益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網頁內容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經權益所有人同意不得將文件中的內容挪作商業或盈利用途。
- 5. 人人文庫網僅提供信息存儲空間,僅對用戶上傳內容的表現方式做保護處理,對用戶上傳分享的文檔內容本身不做任何修改或編輯,并不能對任何下載內容負責。
- 6. 下載文件中如有侵權或不適當內容,請與我們聯系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 舉辦2025年社區八一建軍節活動主題方案
- 基于tms320f280049設計的簡單電路
- 二零二五版授予虛擬股合同
- 二零二五版房屋租賃主體變更三方合同
- 二零二五版房屋買賣合同授權委托書
- 汽車股份轉讓合同二零二五年
- 私有房屋產權買賣協議
- 跨境電商創業實訓計劃
- 信息采集員管理制度
- 鋁業公司生產管理制度
- 網絡系統維護記錄日志表
- 廣東省廣州市白云區2024-2025學年高三下學期2月統測英語試卷【含答案解析】
- 2023-2024學年廣東省廣州市天河區八校聯考七年級(下)期中數學試卷(含答案)
- deepseek的使用技巧與實際應用培訓課件
- 禁食病人護理措施
- 存款保險知識競賽
- 信息技術必修1數據與計算2.2《做出判斷的分支》教學設計
- 七年級生物上冊 3.2.1 種子的萌發說課稿1 (新版)新人教版
- 2025年春季中小學升旗儀式安排表(附:1-20周講話稿)
- 2025年臨床醫師定期考核必考復習題庫及答案(1000題)
- 2024年中國男式印花T-恤衫市場調查研究報告
評論
0/150
提交評論