1、PAGE PAGE 22目 錄 TOC o 1-2 h z HYPERLINK l _Toc305337303 一、編制依據 PAGEREF _Toc305337303 h 2 HYPERLINK l _Toc305337304 二、工程概況 PAGEREF _Toc305337304 h 2 HYPERLINK l _Toc305337305 三、工程地貌及水文地質概況 PAGEREF _Toc305337305 h 3 HYPERLINK l _Toc305337306 3.1、場地地層概況 PAGEREF _Toc305337306 h 3 HYPERLINK l _Toc3053373
2、07 3.2、水文地質條件 PAGEREF _Toc305337307 h 5 HYPERLINK l _Toc305337308 四、基坑降水方案設計 PAGEREF _Toc305337308 h 6 HYPERLINK l _Toc305337309 4.1、設計綜述 PAGEREF _Toc305337309 h 6 HYPERLINK l _Toc305337310 4.2、降水方案設計 PAGEREF _Toc305337310 h 7 HYPERLINK l _Toc305337311 五、施工組織設計 PAGEREF _Toc305337311 h 14 HYPERLINK l
3、 _Toc305337312 5.1、施工準備 PAGEREF _Toc305337312 h 14 HYPERLINK l _Toc305337313 5.2、施工部署和施工工期 PAGEREF _Toc305337313 h 15 HYPERLINK l _Toc305337314 5.3、施工工藝 PAGEREF _Toc305337314 h 15 HYPERLINK l _Toc305337315 5.4、施工方法 PAGEREF _Toc305337315 h 16 HYPERLINK l _Toc305337316 5.5、抽水 PAGEREF _Toc305337316 h 1
4、9 HYPERLINK l _Toc305337317 5.6、基坑內深井封井措施 PAGEREF _Toc305337317 h 19 HYPERLINK l _Toc305337318 5.7、技術要求和質量保證措施 PAGEREF _Toc305337318 h 20 HYPERLINK l _Toc305337319 5.8、安全保證措施 PAGEREF _Toc305337319 h 21 HYPERLINK l _Toc305337320 5.9、文明施工管理規定 PAGEREF _Toc305337320 h 22 HYPERLINK l _Toc305337321 5.10、應
5、急預案 PAGEREF _Toc305337321 h 22附圖:1、降水平面布置圖2、明排水溝位置圖一、編制依據二、工程概況本降水方案對整體基礎開挖水位降深進行預測。擬建物為不規則矩形組合,根據總平面圖按比例用計算機測量地下車庫輪廓線以內開挖面積15432.35m2,開挖深度主樓從地面算起19.8m裙樓從地面算起17.5m,降水水位距離基坑底要求的深度為0.5m,主樓水位從地面算起應為20.3m。裙樓從地面算起18.0m,為了方便計算主樓降水井水位疊加計算選用A點,裙樓降水井水位疊加計算選用B點。然后計算降水井在同步排水時各計算點需要多少天才能達到地基開挖設計的深度。在降水工程布置時還要考慮
6、地基支護和開挖放坡原理,當降水需布在距開挖基坑外2.8m處,這樣經推算降水井工程控制面積可達到18400m2,基礎開挖和預測設計降水布井方案見“基礎開挖降水施工布置圖”。三、工程地貌及水文地質概況3.1、場地地層概況根據巖土工程勘察報告場地地層結構較為復雜,層序穩定,除地表淺部有填土地層外,其下均為第四系沖、湖湘地層,以粉質黏土、粉土、粉沙及細砂為主。在本場地勘察深度范圍內(120m)場地土自上而下分為8層,現以層序分述如下: 第 eq oac(,1)層雜填土(Q4ml):雜色,主要由磚塊,爐渣、建筑垃圾、生活垃圾等組成,稍濕,結構松散,均勻性差。平均厚度在1.92m,層底埋深0.504.80
7、m。 第 eq oac(,2)層粉土(Q4al):褐黃色,局部夾有粉質粘土透鏡體活或薄層。稍濕,呈密實狀態,搖振反應中等,無光澤反應,干強度及韌性低,具中等壓縮性。平均厚度2.46m,層底埋深2.709.60m。 第 eq oac(,2)1 層粉土(Q4al):褐黃色,局部夾薄層粉土層,濕,呈硬塑狀態,無搖振反應,稍有光澤反應,干強度中等,韌性中等,具中等壓縮性。平均厚度2.08m,層底埋深2.5010.30m。 第 eq oac(,3)層粉土(Q4al):褐黃色,局部夾有粉質粘土透鏡體活或薄層。飽和,呈密實狀態,具低壓縮性。平均厚度6.25m,層底埋深8.0026.5m。 第 eq oac(
8、,3)1 層粉土(Q4al):褐黃色,局部夾有粉質粘土透鏡體活或薄層。稍濕,呈密實狀態,搖振反應中等,無光澤反應,干強度及韌性低,具中等壓縮性。平均厚度1.38m,層底埋深10.3013.60m。 第 eq oac(,3)2層粉土(Q4al):褐黃色,局部夾薄層粉土層,濕,呈硬塑狀態,無搖振反應,稍有光澤反應,干強度中等,韌性中等,具中等壓縮性。平均厚度0.88m,層底埋深12.4015.70m。 第 eq oac(,4)層粉土(Q4al):褐灰色,局部夾有粉土、粉質粘土透鏡體或薄層。飽和,呈密實狀態,具低壓縮性。平均厚度10.02m,層底埋深17.3038.20m。 第 eq oac(,5)
9、層粉土(Q4al):褐灰色,局部夾有粉土、粉質粘土透鏡體或薄層。飽和,呈密實狀態,具低壓縮性。平均厚度10.77m,層底埋深35.3055.20m。 eq oac(,5)1層粉土(Q4al):褐黃色,局部夾薄層粉土層,濕,呈硬塑狀態,無搖振反應,稍有光澤反應,干強度中等,韌性中等,具中等壓縮性。平均厚度3.90m,層底埋深41.2047.50m。 第 eq oac(,6)層粉土(Q4al):褐灰色,局部夾有粉土、粉質粘土透鏡體或薄層。飽和,呈密實狀態,具低壓縮性。平均厚度17.96m,層底埋深66.0078.40m。 第 eq oac(,7)層粉土(Q4al):褐黃色,局部夾薄層粉土層,濕,呈
10、硬塑狀態,無搖振反應,稍有光澤反應,干強度中等,韌性中等,具中等壓縮性 。平均厚度9.82m,層底埋深75.586.5m。 第 eq oac(,8)層粉土(Q4al):褐灰色,局部夾有粉土、粉質粘土透鏡體或薄層。飽和,呈密實狀態,具低壓縮性。平均厚度30.82m,層底埋深80.00120.00m。 第 eq oac(,8)1層粉土(Q4al ):褐灰色,飽和,呈密實狀態,搖振反應中等,無光澤反應,干強度及韌性低,具中等壓縮性。平均厚度2.00m,層底埋深92.60m。3.2、水文地質條件1、區域條件:根據當前人文地質成果資料,銀川平原是一呈南北向延伸的地埑式斷陷盆地。第四系以來在基底構造及新構
11、造運動的控制下,盆地內堆積了巨厚的松散沉積物。具地熱鉆探資料,在盆地中心第四系厚度到了1009m。在以細砂為主的地中層,間夾著多層粘砂土、砂粘土。結構松散、顆粒均勻的細砂,是地下水賦存好運動的良好介質。本次建筑物場區正地處銀川沖湖積平原中段西部,地貌類型屬黃河沖湖積二級階地,上部地層結構較為單一,成因類型上為第四系松散沉積。含水層主要由第四系沖湖積細砂、粉細砂組成。上覆地下水以潛水的形式存在,水位埋深在7.27.89m左右,具微承壓性質,區域上劃分為第一含水組,下伏第二含水組均為承壓水。第一含水組巖是本次降水的目的層,區域含水層厚度為5065.0m,下部有較為穩定的隔水 層,單井出水量6001
12、500m3/d左右,滲透系數3.018.87m/d,導壓系數780996m2/d,地下水位埋深在豐水期小于8m,年水位變幅在0.51.0m。 2、場地降水條件:根據巖土工程勘察報告(1)目的層:上覆含水潛水層,鉆孔深度120m已揭穿第一含水巖組,即第一含水層底板埋深在67.878.4m,含水層厚度經統計計算62.78m,物質成分多為細砂層,透水性較強。(2)靜止水位:水文地質勘察報告(抽水試驗)提供水位埋深在7.2-7.89。平均埋深在7.60m。(3)滲透系數:根據野外抽水試驗資料,各種計算方法統計取平均值,細砂滲透系數為5.94m/d。與開挖區東側的銀川凱賓斯基飯店地基開挖降水索取滲透系數
13、5.18m/d基本相符。(4)水位降深設計值:根據自然地面起算高層主樓底層開挖深度-19.8m,開挖區內的水位降深必需在大于12.2m(即水位降至地面-20.3m以下)。裙樓底層開挖深度-17.5m,開挖區內的水位降深必須在大于10.5m(即水位降至地面-18.0m以下)。3、基坑開挖條件:自然地面其算底層開挖深度A點-19.8m,B點開挖深度-17.5m,基坑周邊嚴格采用降水基坑邊坡支護。四、基坑降水方案設計4.1、設計綜述依據建筑物地基開挖的要求,場地地層的水文地質特征及場地周圍建筑物狀況,降水方案設計應滿足以下要求: 1、首先應考慮到降水工作實施后對周圍建筑物的影響。由于降水系統開始工作
14、后,將形成一個以施工場地為中心的地下降水落漏斗,其范圍將隨著水位的下降而不斷擴大,這樣原有建筑物地基的受荷載傳導方式必定改變,且隨地下水位的下降,地基土的可壓縮性增大,建筑物的穩定性將受到影響,因此,地下水降落漏斗的范圍應受到控制,降水井的水位應穩定慢速下降,且控制在一定的區間內。 2、以節約投資為宗旨,投入最少工作量,合理的井距,適宜的井深和井徑,達到水位降深12.2m和10.5m,地面以下-20.3m和18.0m的目標值。 3、為確保降水工程不受基坑開挖工作干擾,以保證水位降深的持續穩定。因此,降水井的布置應在地基開挖線外擴2.8m處成井。 4、排水井布設在開挖區上邊沿以外,并保留一定的放
15、坡位置,利用非穩定流理論計算排水井同步開采時需要幾天才能達到開挖的目的深度。4.2、降水方案設計1、降水井的深度確定 HW=HW1+HW2+HW3+HW4+HW5+HW6 式中:HW降水深度(m); HW1基坑深度(m); HW2降水水位距離基坑底要求的深度(m); HW3降水井分布范圍按水力坡度計算影響深度(m); HW4降水期間的地下水位變幅(m); HW5降水井過濾器工作長度(m); HW6沉砂管長度(m); HW=19.0+0.5+7.5+1+6+1 =35.0m 2、水文地質參數的選取和確定 如前所述,該工程施工場地為不規則矩形形狀,經綜合計算,降水井控制面積為18400m2。 根據
16、區域水文地質條件和現有水文地質資料,同時為了準確取得本次地基開挖降水設計取得的水文地質參數,在場地內布設了抽水主孔和三個觀測孔的穩定流、非穩定流的抽水試驗,第一落程下入50m3/h潛水泵,抽水24h。進行了穩定流抽水試驗,并進行了水位恢復24h。第二落程下入65m3/潛水泵,進行了穩定流抽水試驗,抽水24h,并進行了水位恢復24h。第三落程下入85m3/h潛水泵,按非穩定流完整井抽水試驗程序進行,抽水時間100h,最后也進行了水位恢復觀測工作。本次降水工程所利用的水文地質參數主要用于個落程計算的參數進行統計,認為可信程度較低的較大值和較小值均舍去,最后選取和周邊水文地質參數接近的值的平均值進行
17、利用。 滲透系數取細砂抽水試驗統計值K=5.94m/d,含水層導水系數T=769.5m2/d。給水度采用細砂參數0.18,推算出導壓系數a=4275m2/d。降水井半徑d=0.25m,開挖區A點水位降水為S=12.7m(由靜止水位算起),B點水位將為S=10.4m(由靜止水位算起),又根據降水的水力坡度和距離,推算出抽水井的水位降深應為S主=20.4m時,開挖區內A點水位才能降到12.7m,B點水位才能降到10.4m,含水層有效厚度經計算Ha=62.78m。3、降水方案計算(1)大口井引用半徑的確定 ro=0.564 ro=76.5m(2)影響半徑的確定 R=2S=788m(3)開挖基坑日總出
18、水量計算 Q=16577m3/d (4)試算法求出布井數(n為布井數) Q=Nq=.=16920m3/d n=47眼安全系數取1.28共需60眼井水。根據基坑邊周邊建筑物的條件,基坑內的水位應均勻下降,才能對周邊已有建筑物地基穩定性不產生影響,考慮水泵距離抽水揚程實際出水量和水泵定額出水量現實有一定的差距,因此,用總出水量同水泵小定額15m3/h(360m3/d)之比計算出實際布設井數,共需47眼。(5)單井允許出水量15m3/h(360m3/d),實際采用的井的數和單井出水量nQ。大于基坑總出水量Q,因而熱為布井數計算和推理是合理的,方案是可行的。(6)水位降深預測和抽水時間推算根據所布設的
19、降水井測量出各抽水井離地基開挖區中心的距離,利用潛水完整并非穩定流理論,各抽水井分別采用以下公式計算,最終求得抽水井連續抽水14天時,開挖區計算點A點水位能降到12.7m(地面算起20.32m),B點在抽水井連續16天時水位能降到10.52m(從地面算起18.12m),以滿足于地基開挖的水位降水要求??梢酝茰y出降水12天時地基可以開挖。公式:S=Ha-式中:S降水場區中心點的水位降深(m); Ha含水層有效厚度(m); Q單井允許抽水量m3/d; K含水層滲透系數(m/d); W(u)井函數(無鋼量); = r抽水井距中心點的距離(m); a含水層導壓系數m2/d t試算的抽水時間(天)。抽水
20、井布設距離、參數及抽水疊加降深計算見以下 A點井號距中心點距離R2W()S1.00158.0024964.000.101.783924.130.142.00142.0020164.000.081.983922.240.153.00124.0015376.000.062.233919.800.174.00107.0011449.000.052.513917.110.195.0092.008464.000.042.803914.310.226.0080.006400.000.033.073911.690.247.0070.004900.000.023.333909.170.268.0066.004
21、356.000.023.453908.060.279.0060.003600.000.023.633906.250.2810.0054.002916.000.013.843904.240.3011.0054.002916.000.013.843904.240.3012.0062.003844.000.023.573906.870.2813.0075.005625.000.023.203910.480.2514.0077.005929.000.023.153910.970.2415.0066.004356.000.023.453908.060.2716.0050.002500.000.014.0
22、03902.770.3117.0037.001369.000.014.593897.010.3518.0029.00841.000.005.083892.330.3919.0034.001156.000.004.763895.380.3720.0050.002500.000.014.003902.770.3121.0064.004096.000.023.513907.480.2722.0082.006724.000. 033.023912.160.2323.00102.0010404.000.042.603916.220.2024.00122.0014884.000.062.263919.51
23、0.1725.00137.0018769.000.082.043921.600.1626.00154.0023716.000.101.833923.680.1427.00156.0024336.000.101.813923.900.1428.00162.0026224.000.111.743924.560.1329.00136.0018496.000.082.063921.470.1630.00113.0012769.000.052.413918.110.1931.0091.008281.000.032.823914.100.2232.0070.004900.000.023.333909.17
24、0.2633.0052.002704.000.013.923909.520.3034.0040.001600.000.014.443898.500.3435.0040.001600.000.014.443898.500.3436.00131.0017161.000.072.133920.800.1637.00106.0011236.000.052.533916.930.1938.0083.006889.000.033.003912.380.2339.0059.003481.000.013.673905.930.2840.0036.001296.000.014.653896.480.3641.0
25、016.00256.000.006.263880.870.4842.0022.00484.000.005.633887.010.4343.0038.001444.000.014.543897.520.3544.0020.00400.000.005.823885.170.4545.009.0081.000.007.413869.770.5746.0030.00900.000.005.013892.980.3947.0053.002809.000.013.883903.890.30合計12.27抽水井布設距離、參數及抽水疊加降深計算見下表 B點井號距中心點距離R2W()S1.00100.00100
26、00.000.043.033912.070.232.0078.006084.000.023.523907.380.273.0065.004225.000.023.883903.910.304.0065.004225.000.023.883903.910.305.0078.006084.000.02 3.523907.380.276.00100.0010000.000.043.033912.070.237.001250015625.000.062.603916.240.208.00155.0024025.000.092.193920.170.179.00178.0031684.000.121.9
27、43922.650.1510.00201.0040401.000.15 1.713924.790.1311.00221.0048841.000.181.543926.420.1212.00243.0059049.000.221.383928.010.1113.00268.0071824.000.261.213929.620.0914.00275.0075625.000.281.173930.030.0915.00254.0064516.000.241.303928.740.1016.00225.0050625.000.191.513926.720.1217.00196.0038416.000.
28、141.763924.350.1418.00165.0027225.000.102.083921.300.1619.00137.0018769.000.072.433917.920.1920.00112.0012544.000.052.813914.200.2221.0083.006889.000.033.403908.560.2622.0068.004624.000. 023.793904.770.2923.0068.004624.000.023.793904.7702924.0077.005929.000.023.543907.140.2725.0097.009409.000.03 3.0
29、93911.500.2426.00100.0010000.000.043.033912.070.2327.0092.008464.000.033.193910.510.2528.0098.009604.000.043.073911.700.2429.0058.003364.000.014.103901.740.3230.0027.00729.000.005.623887.050.4331.0027.00729.000.005.623887.050.4332.0061.003721.000.014.003902.700.3133.0097.009409.000.033.093911.500.24
30、34.00133.0017689.000.062.483917.380.1935.00171.0029241.000.112.013921.940.1536.0013158.003364.000.01 4.103901.740.3237.0027.00729.000.005.623887.050.4338.0029.00841.000.005.483888.420.4239.0061.003721.000.014.003902.700.3140.0096.0092160.000.033.113911.310.2441.00134.0017956.000.072.473917.520.1942.
31、00171.0029241.000.112.013921.940.1543.00208.0043264.000.161.653925.380.1344.00126.0015876.000.062.583916.380.2045.00162.0026224.000.102.113920.970.1646.00200.0040000.000.15 1.723924.700.1347.00238.0056644.000.211.423927.670.11合計10.52 4、降水系統方案 本著經濟、合理、切實可行的原則,根據理論計算及本地區的降水經驗,布設降水井60眼(見附圖),井距在基坑外圍約2.8
32、m,井深36m,共布設42眼井,本工程由于場地跨度較大,基坑中部水位下降很慢,根據降水工程面積和以往降水工程經驗,本工程需要在基坑內布設二排降水井,基坑內布設井數18眼,其中排距30m,井深30m,井距30m,該方案共布降水井60眼。所有水井成孔直徑為650,濾水管采用內徑350,外徑450的無砂水泥濾管,濾料選用1mm3mm干凈石英砂,以保證降水井內不會產生大量涌沙確保降水效果。 單井允許出水量15m3/h(360m3/d),實際采用的井點數和單排出水量大于16577 m3/d,并且考慮水泵遠距離輸水,因而認為布井數60眼日排水量超過了16577m3/d是合理的,方案可行。五、施工組織設計5
33、.1、施工準備1)、施工技術準備 . 施工前,應做好平面定位基準點和高程測量控制點的測設和復核工作。. 開工前根據地質勘察報告對各施工部位地段進行詳細的了解,并召開技術交底會,將技術要求及時傳達到機臺班組。. 施工前各項準備工作完畢后,報審降水設計及施工方案。2)、施工現場準備工作 作好施工現場的平整和臨時道路、臨時供水、供電等管線的敷設;臨時設施的搭設;現場照明設備的安裝;材料堆放和儲放; 3)、施工材料準備 .采購合格施工材料,質量證明資料齊全。 .進場材料全部進行復檢,合格后方可使用。 .分階段、分批次組織材料進場,保證施工進度要求。 eq oac(,4)、加強進場材料管理,避免不必要的
34、材料損失、浪費。4)、主要施工機械設備序號名 稱型 號數 量1正(反)循環鉆機FXHJ304臺2潛水泵QS(R)40-39/3-7.538臺3潛水泵QS(R)20-42/3-422臺說明:為保證降水速度和質量,水位能迅速下降,在預定的時間內達到降水深度,并考慮基坑周圍建筑物的安全,基坑周圈降水井內采用“大泵小泵隔一放一”的原則,基坑內的降水井全部采用大功率水泵。. 機械設備進場進行檢修,確保機械設備運行時安全可靠。 . 機械設備進場后經常進行定期或者不定期的檢查,經常對機械設備進行維護、保養。 . 配備足夠的機械設備零部件,以備換用。5)勞動力準備本工程具有工期緊、規模大、標準高等特點。為保證
35、本工程順利施工,將調集精干的隊伍,性能良好的大型專用機械設備來組織施工。用我們類似工程的施工經驗精心組織,精心施工,確保工程如期竣工,為后期結構施工創造條件。降水施工管理和主要技術人員配備如下:序號職務人數序號職務人數1管理人員3人4機械操作手20人2質檢員1人5綜合工40人3安全員1人5.2、施工部署和施工工期本工程的降水為整個工程的前期工程,后期須與土方挖運、結構施工相配合,此工序的質量和工期直接影響到后續工程的進度和質量。為了保證工期,根據地質勘察報告,安排降水井施工在高壓旋噴后進行,第一步挖土深度為3.03.9m,第二層挖土深度為6.06.9m,在第二層挖土前,周邊降水系統具備出水能力
36、。為此應合理安排施工順序,科學組織和管理。本工程抽降水的周期是制約工期的關鍵。為縮短工期,充分利用場地開闊的有利條件組織多臺鉆機平行流水施工,成井、洗井、布置排水管、下泵等多道工序同步進行。降水井用4臺套循環鉆機施工,每天完成8口降水井施工,60口降水井施工總工期10天左右,降水管隨后鋪設完成。5.3、施工工藝降水井采用正(反)循環鉆機成孔,以保證成孔質量。1、降水井施工工藝:施工準備井點定位機械設備就位成孔下管濾料填充洗井試運行運行。 2、排水施工工藝:施工準備放線溝槽開挖集水井、沉淀池砌筑管網安裝試水土方回填。5.4、施工方法1、降水井施工:(1)施工準備:做好場地的“三通一平”工作,組織
37、施工人員、施工材料、施工進場設備。(2)井點定位: eq oac(,1)根據建設單位給定建筑物紅線、建立降水井點平面控制網。 eq oac(,2)利用全站儀、經緯儀定位井點位置,并做好標記。 eq oac(,3)請相關單位進行驗線,并做好記錄。(3)機械設備就位: eq oac(,1)平整機械設備就位的場地,保證機械設備安裝的水平度。 eq oac(,2)對機械設備安裝前檢查、有專業人員進行安裝。 eq oac(,3)安裝完畢后對機械設備進行水平度、垂直度、穩定性檢查。 eq oac(,4)驗收、試運行。(4)成孔:管徑采用鉆孔成孔,直徑650,井管內徑340,井深36米,當鉆孔達到設計深度后
38、,加大進水量沖孔,將空內泥漿沖出,保證井內水的含泥量不大于5%。(5)下管: eq oac(,1)井管采用外徑為420的水泥砂管。 eq oac(,2)將水泥砂管固定在托盤中,將托盤與井管放入井中。 eq oac(,3)井管之間采用土工布纏好并綁扎牢固。 eq oac(,4)濾水管采用雙層濾網管包裹。 eq oac(,5)井管高出地面500mm,以防止地面雜物涌入井內。(6)濾料填充:填充料為優質礫石,井管下孔后徹底換漿,然后從井管四周均勻填料,開始時速度不宜過快,等降水管內出水后加快填料至自然地坪下1米,以上部分粘土回填至地面。(7)洗井:濾料填充完畢后進行洗井,在降水內沉入污水泵,污水泵沉
39、入水面3米以下,洗井時間部少于12小時。(8)試運行:降水井洗井后,安裝潛水泵進行試運行,在抽水過程中測定抽水量、工作水壓力等,并做好記錄,校核實際抽水量與設計計算值是否相符,如有較大偏差時應及時調整降水方案。(9)運行: eq oac(,1)組織專人進行看護,保持水泵、供電系統正常運行。 eq oac(,2)派專人測量水位,水位降至設計水位前每天兩次,水位降至設計水位時每天一次,并做好記錄。 eq oac(,3)根據水位觀測情況指導水位的開挖。 eq oac(,4)降水周期由設計單位確定。2、暗埋排水系統施工:(1)施工準備: eq oac(,1)組織人員、機械設備、施工材料進場。 eq o
40、ac(,2)熟悉圖紙、方案、明白設計意圖和施工要點。 eq oac(,3)進行施工人員的安全技術交底。 eq oac(,4)現場布置及水、電準備。(2)放線:根據給定控制線利用全站儀、經緯儀、水準儀、卷尺定位出施工井點、管溝、沉淀池位置標高,并做好標識記錄。(3)土方開挖:土方開挖采用小型機械開挖,挖出的土方就近堆放,以便回填。(4)集水井、沉淀池砌筑: eq oac(,1)人工平整土方、澆注100厚C10混凝土墊層 eq oac(,2)集水井、沉淀池砌筑采用粘土磚砌筑。集水井要滿足上人要求,并設置鋼筋上下人梯,長1600mm,厚240mm,M5水泥砂漿砌筑,高出地面200mm。 eq oac
41、(,3)井(池)內壁用1:3的防水砂漿抹20mm厚做找平層,其內表面要抹平壓光,陰陽角做半徑為50mm圓弧后做兩道1mm厚JS型防水涂料,防水涂料表面抹20mm厚砂漿保護層;流水槽使用混凝土,且高度不小于排水管徑的四分之三;現場設三個排水出口,使用三級沉淀池后排入市政管網。(5)管網安裝: eq oac(,1)降水井內至集水井采用管徑110mm聚乙烯塑料管,利用噴燈、鐵絲捆扎接頭。 eq oac(,2)集水井以內采用內徑400mm波紋管,管道底部鋪200mm厚細砂,接縫部位打入發泡膠,保證密實,接口部位外灌C20細石混凝土防止滲漏。排水管道坡度為0.1%0.3%,坡向沉淀池。波紋管地埋,考慮到
42、冬季施工,埋設深度不小于1.1米。集水井與波紋管接頭部位采用細石混凝土灌注,管子四周砼厚度不小于100mm(6)閉水試驗:管網安裝完畢后利用降水井向排水系統內注水,灌滿水后浸泡24小時,進行閉水試驗,檢查是否滲漏,對滲漏點進行修復。(7)土方回填:閉水結束后,進行土方回填,第一層細砂,回填厚度高于灌頂200,不進行夯實。以上每層厚度300,利用平板夯夯實。3、明排水溝施工:基坑降水方案中以暗埋排水系統為主,考慮到暗埋排水系統在使用過程中不宜監測,系統失效時返修處理的時間長,且處理期間降水工作不能停止;萬一暗埋排水系統失效后處理不及時,導致基坑涌水,影響基坑錨索支護體系,不僅安全隱患大,而且對地
43、下結構的危害性也極大。故,考慮到暗埋排水系統的這一弊端及提高應急處理的能力,冠梁邊做一套備用的明排水系統,排水能力不低于暗埋排水系統。在2011年冬期施工和地下兩層結構施工期間,采用明排水系統。冠梁邊做一套備用明排水溝:明溝寬400mm,溝深700mm,明溝采用M5水泥砂漿砌筑粘土磚,壁厚240mm;為防止降水過程中因不均勻沉降導致溝底開裂滲水,故溝底需加強處理。溝底原土夯實后做500厚3:7灰土墊層,再澆筑200mm厚C20細石混凝土墊層;溝壁內側抹1:3防水砂漿找平層,其上刷2道1mmJS防水涂料,表面再做20mm厚1:3水泥砂漿保護層。排水溝上覆蓋成品混凝土篦子,尺寸為400X600X3
44、5。具體位置及做法見附圖。5.5、抽水本工程降水時間長,降水施工期間成立由機電部負責的降水施工隊,晝夜24小時監護,確保降水的連續性和降水施工的成功。降水井開始抽水時水泵不能一次性放到井底進行大降深抽水,否則井中水躍值過大,反復幾次將破壞井管和所填濾料,造成井內大量涌沙現象,抽出的水中含沙量太大,深井淤積而報廢。抽水電泵應每次下放3m5m。5.6、基坑內深井封井措施基坑內的降水井在降水任務完成后進行回填封井,具體措施如下:1、在施工底板砼前井口放置3mm厚直徑為400mm的鋼護筒,安裝高度為高出底板頂面5厘米,保證降水井繼續抽水。鋼護筒外圍預設兩道鋼圈,第二道鋼圈設防水密封橡膠墊、壓緊鋼板,防水層施工壓其上。具體做法見下圖,底板砼達到一定強度后吊出水泵開始封井。 封井示意圖2、封井時井內采用級配砂石回填,填至底板底標高
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯系上傳者。文件的所有權益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網頁內容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經權益所有人同意不得將文件中的內容挪作商業或盈利用途。
- 5. 人人文庫網僅提供信息存儲空間,僅對用戶上傳內容的表現方式做保護處理,對用戶上傳分享的文檔內容本身不做任何修改或編輯,并不能對任何下載內容負責。
- 6. 下載文件中如有侵權或不適當內容,請與我們聯系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 萬某租房合同范本
- 預防臺風小常識
- 保安規范著裝標準
- 護理面試操作教程
- 項目系統管理
- 音樂療法在手術中的應用
- 美學行業就業分享
- 2021年廣西公辦高職高專院校招生聯盟單獨考試招生聯合測試考試大綱及樣題
- 2025年山西省呂梁市部分學校中考一模地理試題(含答案)
- 深圳職業技術大學《現代審計學(英語)》2023-2024學年第二學期期末試卷
- TGIA 004-2020 垃圾填埋場地下水污染防治技術指南
- GB/T 70.1-2008內六角圓柱頭螺釘
- 《農業保險學》第7章畜牧保險
- 2023年初中生物會考試卷、參考答案、答題卡(2023年)
- 現澆墩臺身軸線偏位、全高豎直度檢測記錄表
- 精品試題人教版八年級物理下冊第十一章-功和機械能專題測試試卷(含答案詳解)
- 發電機保養檢查記錄表
- 內懸浮內拉線抱桿分解組塔施工方案
- 《音樂表演專業畢業實習》教學大綱
- 危險化學品(專項)安全檢查表(樣表)
- 冀教版三年級數學數據收集和整理
評論
0/150
提交評論